Montage Gold Corp. (“Montage” or the “Company”)
(TSXV: MAU, OTCQX: MAUTF) is pleased to announce that it has
launched the construction of its Koné project in Côte d’Ivoire
(“Koné” or the “Project”) with first gold production scheduled for
Q2-2027. To mark this significant milestone, a groundbreaking
ceremony was held at Koné today with a strong presence from
government officials and local communities, demonstrating their
support for the project given its significant social and economic
benefits.
Significant progress is being made to rapidly
advance and derisk the project as early works are well underway and
major construction works are set to commence in the coming weeks,
once further construction equipment arrives to site. The
engineering, procurement and construction management (“EPCM”)
contract has been awarded to Lycopodium Minerals Pty Ltd
(“Lycopodium”), with a number of tasks to be self-performed by
Montage’s experienced in-house construction team which already
totals approximately 350 people. Montage, together with Lycopodium,
have completed a comprehensive engineering review of Montage’s
Updated Feasibility Study (“UFS”) published in January 2024 which
has resulted in the optimization of several key design parameters
to enhance the crushing and milling circuit and improve the
efficiency of the overall operation. The project is fully funded
with significant headroom with upfront capex expected to be US$835
million while Montage has in excess of US$900 million in liquidity
sources.
Martino De Ciccio, CEO of Montage, commented:
“We are very pleased to announce the commencement of construction
at the Koné project in Côte d'Ivoire, marking a significant
milestone in our journey to becoming a premier African gold
producer and the culmination of this year’s efforts.
Our ability to rapidly advance the project is
driven by the strong partnerships we have built, based on a win-win
approach, with local stakeholders, strategic investors, financiers,
suppliers, and contractors. We are also grateful for the dedication
of our experienced management team, and we thank everyone involved
for their commitment.
Looking ahead, we are excited to continue
unlocking value for all our stakeholders by advancing our
construction efforts, while also creating value through exploration
and by expanding our focus on social, health, education, and
economic programmes for our local communities.”
Peder Olsen, President and Chief Development
Officer of Montage, commented: "We are excited to launch the
construction of the Koné project, which marks the culmination of
our efforts to optimize key design parameters aimed at enhancing
the crushing and milling circuit and improving the efficiency of
the overall operation. Additionally, to mitigate construction
risks, we have strategically placed orders for long-lead items,
securing both price stability and timely delivery.
Given the high quality of our project and our
intention to create a leading African gold producer, we are proud
to have assembled a highly experienced and skilled construction
team. Many of these team members have worked with me to
successfully deliver four projects over the last decade in West
Africa, including two in Côte d’Ivoire.
I would like to take this opportunity to thank
everyone who has contributed to getting us to this point. As the
ideal time to begin construction is after the rainy season, we are
excited to have commenced early works at the optimal time. We now
look forward to delivering on our construction schedule and
unlocking significant value for all stakeholders."
GROUNDBREAKING CEREMONY
Earlier today, a groundbreaking ceremony was
held at Koné with over 2,000 people present including a strong
presence from government officials and local communities,
demonstrating their support for the project, as shown in Figure 1
below. At the ceremony, Mamadou Sangafowa-Coulibaly, Côte
d’Ivoire’s Mines, Petroleum and Energy Minister reiterated the
country’s support for the mining sector and the Koné project in
particular, outlining the significant social and economic benefits
to all stakeholders.
Figure 1: Groundbreaking
ceremony
PROJECT CONSTRUCTION UPDATE
EPCM awardThe Company has
awarded the engineering, procurement and construction management
(“EPCM”) contract to Lycopodium Minerals Pty Ltd (“Lycopodium”).
Lycopodium’s involvement in the project commenced in 2018 and were
the engineers for Montage’s Definitive Feasibility Study (“DFS”)
and Updated Feasibility Study (“UFS”). In addition, Lycopodium has
a strong track record in West Africa and in particular in Côte
d’Ivoire, having recently completed construction of Fortuna Mining
Corp’s Séguéla project in 2023 and Endeavour Mining Plc’s Lafigue
mine in 2024, both on time and on budget. Other projects in Côte
d’Ivoire completed by Lycopodium include the Yaouré project for
Perseus Mining Ltd, and Endeavour Mining Plc’s Ity CIL and Agbaou
projects. Integrating fully into the owner’s team, Lycopodium is
responsible for providing Montage with support on the engineering,
design, procurement, construction management and commissioning of
the processing plant and process related infrastructure.
Order of long-lead itemsA
significant number of long lead item orders have been committed to
by Montage, securing pricing for equipment and services on initial
capital of over US$150 million, with key orders placed
including:
- Ball mill,
high-pressure grinding rolls (“HPGR”) and crushers (primary and
secondary)
- Thickeners and
CIL tanks
- Key earthworks
mobile equipment leases
- Early camp
facilities are complete while construction of the permanent camp is
underway which will also accommodate construction personnel
Early works Early works were
launched in Q4-2024 and are progressing well with the following key
highlights:
- No lost time
incidents (“LTIs”), with over 138,890 workhours completed since the
commencement of early works
- In line with its
commitment to local content, Montage has partnered with the
government-accredited Lycée Technique de Mankono to deliver
practical vocational training programs tailored to the needs of the
Koné project for an initial 80 individuals. The first group of
participants, drawn from impacted local communities, has
successfully completed its training and is now commencing
employment with Montage. This first group includes steel fixers,
building electricians, masons, carpenters and plumbers. The second
group of trainees began its practical training on October 21,
2024
- In addition,
Montage is pleased to be using local contractors for buildings,
earthworks and camp electricals
- Montage has
initiated a literacy and numeracy program for individuals in nearby
affected villages. Currently over 500 participants are attending
the programme which aims to empower local communities with
essential skills to pursue employment and improve access to
economic opportunities and enhance long-term socio-economic
resilience
- Land
compensation and resettlement activities have begun with access
secured to all major early works areas including the plant, camp,
water storage facility and the tailings storage facility
(“TSF”)
- The resettlement
site for the relocation of the Village of Dolourougokaha has been
agreed between affected and host communities with housing
construction set to commence in late Q1-2025
- With Koné
located in a low water stress area, project water will be sourced
from the nearby Marahoué river into a water storage facility
(“WSF”) and from pit dewatering with a supplementary borefield. The
Ministry of Water and Forests granted the required water
abstraction authorizations in Q3-2024 and compensation for access
clearing for the pipeline is commencing
- Earthworks are
underway for the access road construction, clearing of major work
areas, and stockpiling of topsoil is ongoing
- Permanent camp
construction has begun with the construction of the first 40-man
blocks well advanced
- Montage is also
focusing on developing an Ivorian supply chain utilising local
supply for project and camp consumables, and is advancing major
contracts to procure fuel, cement, aggregates and explosive
supplies, as well as sustainable food sources
- Power will be
drawn from the national grid operator, Compagnie Ivoirienne
d’Electricite (“CIE”), via a new 225kV transmission line connecting
to existing power lines located approximately 20km from the
processing plant area. Natural gas and hydro-electric generation
account for approximately 70% and 20% of Côte d’Ivoire’s
electricity generation1 with expansions projects underway to
install an additional 1,448MW of natural gas and 297MW of
hydro-electric generation capacity. The CIE has confirmed capacity
to meet the demand requirements for the Koné project and Montage
has conducted a power system study with CIE which supports the
delivery of high quality power, without additional support
measures.
Figure 2: Early works
underway
Engineering
optimizationsFurther to Montage’s Updated Feasibility
Study (“UFS”) published on January 16, 2024, Lycopodium and Montage
have undertaken a comprehensive Front-End Engineering and Design
process which has resulted in the optimization of several key
design parameters to enhance the crushing and milling circuit and
improve the efficiency of the overall operation.
The plant nominal throughput as per the UFS is
11.0 Mtpa, based on a primary crushing, secondary crushing and
HPGR, milling and carbon-in-leach (“CIL”) availability of 75%, 88%
and 91% respectively. The following engineering improvements have
subsequently been made:
- The primary
crusher has been upgraded with 33% extra power capacity (from 450kW
to 600kW) and the eccentric speed has been increased, which
generates the potential to increase the throughput.
- The secondary
crushers have been upsized by 50% from (from 600kW to 930kW) to
ensure that the secondary crushing circuit, which typically has an
availability of 75%, can match the full availability of the
HPGR.
- The two HPGR's
have been replaced with a single larger unit for ease of
maintenance, as well as the ability to accept a coarser feed
size.
- The HPGR circuit
includes a stockpile in lieu of a surge bin which is expected to
provide significantly greater operating flexibility.
- Ball mill
installed power has increased by 10% with a single ball mill of
22MW which compared to the two 10MW ball mills previously
considered. This single larger mill will be simpler to operate
given that the addition of low-speed synchronous motors has
eliminated the need for gearboxes in the drive train, reducing
components that need auxiliary cooling systems, maintenance and
spares.
- The twin seven
tank CIL trains provide a combined slurry residence time of 36
hours for the 10% oxide / 90% fresh ore blend. Should Montage
decide to further increase the mill throughput, provisions have
been made to add an extra tank to each train to either improve
residence time or maintain it with the potential to increase
throughput.
- Montage
continues to engineer the potential addition of an oxide circuit
consisting of a sizer and conveyor to directly feed the mill with
oxide and transitional material, bypassing the hard rock
comminution and HPGR. The current design limits oxide material to
10% of total feed, and requires 18.8Mt of pre-stripping,
stockpiling, and gradual reintroduction of oxide material into the
feed over the first eight years of production. An oxide circuit
would enable an earlier first gold pour while the hard rock
comminution is being commissioned, reduce rehandling costs for
oxide ore mined in pre-production, provide significant operational
flexibility to continue production during maintenance of the
crushing circuit and would improve blending optionality. While
oxide feed is limited within the Koné deposit, Montage’s ability to
discovery more oxide material across new and existing targets will
be a determining factor in forming an investment decision for the
oxide circuit.
Based on these optimization modifications, the
treatment plant design now incorporates crushing, screening, HPGR,
grinding and classification, pre-leach and tailings thickening, CIL
circuit, carbon recovery and acid wash, carbon elution,
electrowinning trains and smelting, as further detailed below:
- Primary crushing
using a gyratory crusher Metso 54/75 and 600kW drive
- Coarse ore
stockpile with 24 hours live capacity (34,200 tonnes) complete with
three 50% capacity reclaim apron feeders
- Closed-circuit
secondary crushing and screening with nominally duty stand-by
cone crushers, Metso MP1250 and 930kW drives, and double deck
multi-slope screens, Schenck 4397, to produce a crushed product
size P80 of approximately 32mm
- HPGR, Metso
HRC2400e with dual 3.0MW drives to produce a nominal P80 of
6mm
- Covered HPGR
product stockpile with a live capacity of 4 hours (4,800 tonnes)
complete with two reclaim belt feeders
- HPGR product wet
sizing/re-pulping screens, Schenck 4397, with undersize slurry
reporting to the milling circuit via the cyclone feed hopper
- HPGR screen
oversize stockpile complete with three 50% capacity vibrating
reclaim feeders
- Primary ball
mill, Metso Φ8.53 metre diameter 14 metre long 22MW dual
pinion, in closed circuit with 2 clusters of 14 each 500mm
diameter hydrocyclones to produce a grind size with a P80
of 75µm
- Pre-leach
thickening (44 metre diameter high rate) to increase the slurry
density feeding the carbon in leach, CIL, circuit to minimise
tankage and reduce overall reagent consumption
- Leach circuit
incorporating 14 leach tanks, arranged in two parallel trains of
seven each in series, to provide 36 hours leach residence time, and
equipped with external oxygen contactors, while provisions have
been made to add an extra tank in the future if required
- Twin 17 tonne
split AARL elution circuits, electrowinning and gold smelting to
recover gold from the loaded carbon to produce a gold/silver
doré
- Tailings
thickening (44 metre diameter high rate) to recover cyanide and
recycle process water from the CIL tailings
- Tailings pumping
to the TSF complete with a supernatant reclaim and return
system
- River water
abstraction system from the Marahoué river and 32km pipeline
Based on the above-described optimization
modifications, the total process plant capital cost has increased
by US$33 million, or approximately 10%. Based upon a comprehensive
review of total project costs accounting for scope changes,
realized tender prices, more conservative working capital
assumptions (to account for greater volumes of spares and
reagents), inclusion of a livelihood restoration programme, and a
higher contingency. Consequently, the total capital cost estimate
has increased by approximately 12%, from US$742 million to US$835
million, compared to the UFS, as shown in Table 1 below. The UFS
assumed US$30 million of vendor financing, mainly related to the
mining contractor mobilization, which reduced the upfront capital
to US$712 million, whereas given the strong liquidity sources
secured by Montage, vendor financing is currently no longer being
contemplated for contract mining.
Table 1 – Koné project capital
expenditure, in US$m
Main Area |
Previous UFS CAPEX |
Updated CAPEX |
Variance |
($M) |
($M) |
($M) |
% |
Process Plant |
338 |
371 |
+33 |
+10% |
Mining and contractor
mobilization1 |
87 |
78 |
(9) |
(10%) |
EPCM & Owners Costs |
69 |
67 |
(2) |
(3%) |
Camp & Other
Infrastructure |
64 |
60 |
(4) |
(6%) |
Tailings and Water
Storage |
55 |
60 |
+5 |
+8% |
Grid Connection |
26 |
31 |
+5 |
+18% |
Compensation, Resettlement &
Livelihood Restoration |
9 |
22 |
+13 |
+135% |
Pre-Production, Start-up &
Commissioning |
13 |
19 |
+6 |
+49% |
Taxes |
5 |
8 |
+3 |
+63% |
Working Capital |
11 |
35 |
+24 |
+231% |
Contingency |
65 |
83 |
+18 |
+27% |
Total CAPEX |
742 |
835 |
+93 |
+12% |
Vendor Finance (Mining
Mobilisation and Camp) |
(30) |
- |
+30 |
+100% |
Total upfront capital |
712 |
835 |
+123 |
+17% |
1UFS assumed vendor financing for the mining contractor
mobilization while the updated estimate does not consider vendor
financing given Montage’s available liquidity sources
Foreign exchange rates of 1.08 for USD:EUR,
0.053 for USD:ZAR, 1.56 for USD:AUD and 1.26 for USD:GBP have been
used to determine capital cost estimates.
Timetable to First Gold PourAs
shown in Figure 3 below, first gold pour is targeted for Q2-2027,
based on a 27-month construction period for the process plant. As
noted, early works are well underway and major construction works,
as well as water storage and dam construction, are due to commence
in early Q1-2025.
Figure 3 – Koné project timeline to first
gold pour
Work Stream |
Q4-2024 |
Q1-2025 |
Q2-2025 |
Q3-2025 |
Q4-2025 |
Q1-2026 |
Q2-2026 |
Q3-2026 |
Q4-2026 |
Q1-2027 |
Q2-2027 |
Early Works |
|
|
|
|
|
|
|
|
|
|
|
FID & EPCM Award |
* |
|
|
|
|
|
|
|
|
|
|
Detailed Design & Engineering |
* |
* |
* |
|
|
|
|
|
|
|
|
Order & Procure Long Lead Items |
* |
* |
|
|
|
|
|
|
|
|
|
Tailings Dam &
Water Dams |
|
|
|
|
|
|
|
|
|
|
|
Tailings Dam |
|
|
|
|
* |
* |
* |
|
|
|
|
Water Storage & Dam |
|
* |
* |
|
|
|
|
|
|
|
|
Construction |
|
|
|
|
|
|
|
|
|
|
|
Power Supply |
|
|
* |
* |
* |
* |
* |
|
|
|
|
Site Infrastructure |
|
* |
* |
* |
* |
* |
* |
* |
|
|
|
Earth works & Concrete Works |
|
* |
* |
* |
* |
* |
* |
|
|
|
|
Structural, Mechanical, Piping |
|
|
|
* |
* |
* |
* |
* |
* |
|
|
Electrical |
|
|
|
|
|
* |
* |
* |
* |
|
|
Process Plant Commissioning |
|
|
|
|
|
|
|
|
* |
* |
|
First Gold |
|
|
|
|
|
|
|
|
|
|
* |
Exploration UpdateMontage
remains on track to achieve its previously published target of
discovering more than 1 million ounces of Measured and Indicated
resources, at a grade 50% higher than the Koné deposit, to be
achieved before the commencement of production.
2024’s first drill campaign was completed at the
end of July, totalling 30,170 metres, with the goal of prioritizing
key targets for the next drill programme. This first programme
successfully confirmed mineralisation at all 14 targets tested. A
second 2024 drilling campaign, totalling 60,000 metres, commenced
in mid-September and to date has achieved 45,000 meters. Montage
remains on track to incorporate the 2024 drilling data into its
year-end resource statement, with a maiden mineral resource
expected to be published in Q1-2025.
In line with Montage’s goal of unlocking
exploration value, the Company expects to conduct similar
exploration efforts in 2025, while construction activities are
ongoing.
Grant of stock incentivesGiven
the recent hires, the Company has granted a total of 347,124
Restricted Share Units (“RSUs”) to non-executive team members. The
RSUs are granted in accordance with the Company’s 2024 Omnibus
Equity Incentive Plan. The RSUs are subject to vesting
provisions.
Neither TSX Venture Exchange nor its
Regulation Services Provider accepts responsibility for the
adequacy or accuracy of this release.
ABOUT MONTAGE GOLD Montage Gold
Corp. (TSXV: MAU) is a Canadian-listed company focused on becoming
a premier multi-asset African gold producer, with its flagship Koné
project, located in Côte d’Ivoire, at the forefront. Based on the
Updated Feasibility Study published in 2024, the Koné project has
an estimated 16-year mine life and sizeable annual production of
+300koz of gold over the first 8 years and is expected to enter
production in Q2-2027.
TECHNICAL
DISCLOSUREMineral Resource and Reserve
EstimatesThe Koné and Gbongogo Main Mineral Resource
Estimates were carried out by Mr. Jonathon Abbott of Matrix
Resource Consultants of Perth, Western Australia, who is considered
to be independent of Montage Gold. Mr. Abbott is a member in good
standing of the Australian Institute of Geoscientists and has
sufficient experience which is relevant to the commodity, style of
mineralisation under consideration and activity which he is
undertaking to qualify as a Qualified Person under NI 43–101.
The Mineral Reserve Estimate was carried out by
Ms. Joeline McGrath of Carci Mining Consultants Ltd., who is
considered to be independent of Montage Gold. Ms. McGrath is a
member in good standing of the Australian Institute of Mining and
Metallurgy and has sufficient experience which is relevant to the
work which she is undertaking to qualify as a Qualified Person
under NI 43–101.
2024 ExplorationAll exploration
work on Kone project is designed and carried out under the
supervision of Montage Gold Corp, Executive Vice President,
Exploration, Silvia Bottero, a registered Professional Natural
Scientist with the South African Council for Natural Scientific
Professions (SACNASP) and Qualified Person as defined in National
Instrument 43-101 developed by the Canadian Securities
Administrators.
Samples used for the results described above
come from Diamond Drilling Holes and are based on 1 metre composite
sample. Core samples have been cut in two by core blade at the camp
facilities then shipped by road to Bureau Veritas facility in
Abidjan, Côte d’Ivoire.
For RC drilling, samples were collected over 1
metre downhole intervals from the base of the cyclone and split
with a three-tier riffle split. Three kilograms samples were
collected then shipped by road to Bureau Veritas facility in
Abidjan, Côte d’Ivoire. All samples have been crushed to 2mm (80%
passing) with 1 kilogram split out for pulverization to 75μm (85%
passing) then analysed by fire assay using a 50-gram charge.
Field duplicate samples are taken, and blanks
and standards are inserted by Montage geologists into the sample
sequence at a rate of one of each sample type per 25 samples. This
ensures that there is a minimum 4% QA/QC sample insertion rate
applied to each fire assay batch. The sampling and assaying are
monitored and audited through analysis of these QA/QC samples by a
consultant independent of Montage. QA/QC has been designed to be in
line with industry best standards and to follow NI 43-101 standards
and the interpretation reviewed by the Qualified Person. Individual
batches are monitored for Standard and Blank failure during import
to the database, whilst longer term QAQC trends are monitored on a
periodic basis by Jonathan Hunt, independent consultant of Montage
and Chartered Geologist of the Geological Society of London.
Results for exploration drillholes used the
following parameters: 0.3 g/t Au cut off for samples, 0.5 g/t Au
minimum value composite and 2.0 metre maximum interval dilution
length. Composite intervals represent (apparent) downhole
thickness. “Including” represents >10 g/t Au.
For further details of the assumptions,
parameters and methods used to develop the Mineral Resource
Estimates and the Mineral Reserve Estimate for the Koné Gold
Project, please see the UFS, entitled "Koné Gold Project, Côte
d'Ivoire Updated Feasibility Study National Instrument 43-101
Technical Report" and filed on SEDAR+ at www.sedarplus.ca. Readers
are encouraged to read the UFS in its entirety, including all
qualifications, assumptions and exclusions that relate to the
details summarized in this news release. The UFS is intended to be
read as a whole, and sections should not be read or relied upon out
of context.
Processing plant reviewStephan
Buys, who is an Extractive Metallurgist with Lycopodium,
independent to Montage, and fellow of AusIMM, is a Qualified Person
under NI 43-101 and has reviewed and approved the scientific and
technical information contained in this news release concerning the
process plant. Mr. Buys has 30 years of experience in plant design,
operations, and research in Africa, Australia, Southeast Asia and
South America's metals and minerals processing industry.
QUALIFIED PERSONS STATEMENTThe
scientific and technical contents of this press release have been
verified and approved by Silvia Bottero, BSc, MSc, a Qualified
Person pursuant to NI 43-101. Mrs. Bottero, EVP Exploration of
Montage, is a registered Professional Natural Scientist with the
South African Council for Natural Scientific Professions (SACNASP),
a member of the Geological Society of South Africa and a Member of
AusIMM.
CONTACT INFORMATION
For Investor Relations Inquiries:Jake CainStrategy
& Investor Relations Managerjcain@montagegold.com+44 7788 687
567 |
For Media Inquiries:John VincicOakstrom
Advisorsjohn@oakstrom.com +1-647-402-6375 |
For Regulatory Inquiries:Kathy LoveCorporate
Secretary klove@montagegold.com+1-604-512-2959 |
|
|
|
FORWARD-LOOKING STATEMENTSThis
press release contains certain forward-looking information and
forward-looking statements within the meaning of Canadian
securities legislation (collectively, “Forward-looking
Statements”). All statements, other than statements of historical
fact, constitute Forward-looking Statements. Words such as “will”,
“intends”, “proposed” and “expects” or similar expressions are
intended to identify Forward-looking Statements. Forward-looking
Statements in this press release include statements related to the
Company’s objectives of achieving first gold pour in the second
quarter of 2027; expected enhancements of key design changes to the
process plant; being fully funded with significant headroom with
respect to the updated capital expenditure estimates; discovering
more than 1 million ounces of higher-grade measured and indicated
resources at a grade 50% higher than the Koné deposit and the
timing thereof; targeted publication of a maiden mineral resource
estimate in the first quarter of 2025; the Company’s mineral
reserve and resource estimates; the Company being on track to
deliver stellar results; the timing and amount of future production
from the Koné Gold Project; anticipated mining and processing
methods of the Koné Gold Project; anticipated mine life of the Koné
Gold Project; targeted improvements in the production profile;
expected timing of completion of our stated drill programs in 2024;
results of the drill programs including targeted additions to the
estimated mineral resources at the Koné Gold Project, and the
timing thereof; expected recoveries and grades of the Koné Gold
Project; timing in respect of future stages of major construction
works, and the length of construction, of the mining operations at
the Koné Gold Project; and timing for permits and concessions.
Forward-looking Statements involve various risks
and uncertainties and are based on certain factors and assumptions.
There is no assurance that any economic satellite deposits will be
discovered, and if discovered ever developed or mined. There can be
no assurance that any Forward-looking Statements will prove to be
accurate, and actual results and future events could differ
materially from those anticipated in such statements. Important
factors that could cause actual results to differ materially from
the Company's expectations include uncertainties inherent in the
preparation of mineral reserve and resource estimates and
definitive feasibility studies such as the Mineral Reserve Estimate
and the UFS, and in delineating new mineral reserve and resource
estimates, including but not limited to, assumptions underlying the
production estimates not being realized, incorrect cost
assumptions, unexpected variations in quantity of mineralized
material, grade or recovery rates being lower than expected,
unexpected adverse changes to geotechnical or hydrogeological
considerations, or expectations in that regard not being met,
unexpected failures of plant, equipment or processes (including
construction equipment), delays in or increased costs for the
delivery of construction equipment and services, unexpected changes
to availability of power or the power rates, failure to maintain
permits and licenses, higher than expected interest or tax rates,
adverse changes in project parameters, unanticipated delays and
costs of consulting and accommodating rights of local communities,
environmental risks inherent in the Côte d’Ivoire, title risks,
including failure to renew concessions, unanticipated commodity
price and exchange rate fluctuations, delays in or failure to
receive access agreements or amended permits, and other risk
factors set forth in the Company’s 2023 Annual Information form
available at www.sedarplus.ca, under the heading “Risk Factors”.
The Company undertakes no obligation to update or revise any
Forward-looking Statements, whether as a result of new information,
future events or otherwise, except as may be required by law. New
factors emerge from time to time, and it is not possible for
Montage to predict all of them, or assess the impact of each such
factor or the extent to which any factor, or combination of
factors, may cause results to differ materially from those
contained in any Forward-looking Statement. Any Forward-looking
Statements contained in this press release are expressly qualified
in their entirety by this cautionary statement.
1Source: International Energy Agency at
www.iea.org/countries/cote-divoire/electricity
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/e7c33816-58bc-4d30-ba54-21cdfe372ecc
https://www.globenewswire.com/NewsRoom/AttachmentNg/96680ae7-eb05-41d5-a8ff-c3f8ea151950
Montage Gold (TSXV:MAU)
과거 데이터 주식 차트
부터 11월(11) 2024 으로 12월(12) 2024
Montage Gold (TSXV:MAU)
과거 데이터 주식 차트
부터 12월(12) 2023 으로 12월(12) 2024