Update on Kiewit Project
10 7월 2014 - 8:00PM
PR Newswire (US)
Clifton Mining Company (OTCBB: CFTN)
ALPINE, UT, July 10, 2014 /PRNewswire/ - Desert Hawk Gold
Corp. has provided the Company with the following update: the
construction on the heap leach pad, including the plastic liner,
have been installed along with the necessary roads and water
diversion. The process plant and assay lab are under
construction. 150,000 tons of overburden have already been
removed in preparation for mining ore and eight thousand tons of
ore have been mined and are stockpiled next to the newly installed
crusher.
Clifton trades on the U.S. OTC: (CFTN).
Note: Any statements released by Clifton Mining
Company that are forward looking are made pursuant to the safe
harbor provisions of the Private Securities Litigation Reform Act
of 1995. Editors and investors are cautioned that forward
looking statements invoke risk and uncertainties that may affect
the company's business prospects and performance.
SOURCE Clifton Mining Company
Copyright 2014 PR Newswire
Clifton Mining (PK) (USOTC:CFTN)
과거 데이터 주식 차트
부터 11월(11) 2024 으로 12월(12) 2024
Clifton Mining (PK) (USOTC:CFTN)
과거 데이터 주식 차트
부터 12월(12) 2023 으로 12월(12) 2024
Clifton Mining Corp (PK) (OTC 시장)의 실시간 뉴스: 최근 기사 0
More Clifton Mining Company News Articles