Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF)
(the “Company” or “Orezone”) is pleased to provide an update on its
ongoing hard rock expansion at its Bomboré Gold Mine. The hard rock
expansion, which is scheduled to commence operations in Q4-2025, is
forecasted to increase gold production by approximately 50%, to
over 170,000 ounces per year. Expansion progress and milestones
achieved to date include:
-
Early mobilization of the concrete contractor 3-months
ahead of schedule, providing for multiple weeks of flexibility in
the project schedule.
-
Foundations are progressing on multiple fronts, with CIL
ring beams and pedestals for the ore bin and trash screen now
complete. Foundations for the dump pocket and SAG mill are
underway.
-
Engineering is ahead of schedule, with all bulk quantities
in line with budget.
-
Procurement is at 82% of total supply value awarded with
all long lead equipment ordered.
-
SAG mill major components are en route to site, well ahead
of schedule for longest lead items.
-
Structural, Mechanical, and Piping (“SMP”) contract
awarded, with contractor mobilization to begin in
March.
-
Tailings Storage Facility (“TSF”) expansion earthworks
commenced.
-
First batch of contractor’s large-capacity mining fleet now
in service, with systematic training ongoing.
-
Preparations for hard rock mining advancing, with
construction of the explosives magazine complete.
Patrick Downey, President and CEO stated,
“Following a strong end to 2024, where we achieved production
guidance for a second consecutive year since commissioning the
oxide plant, I am pleased to report that the hard rock expansion is
progressing ahead of schedule and on budget. This is a testament to
the experience and dedication of the Orezone team, who was also
responsible for constructing the Bomboré oxide plant on time and
under budget.
Completion of this first stage of the hard rock
expansion will mark a significant milestone at Bomboré, with gold
production set to increase approximately 50% from current levels,
to over 170,000 ounces per year. With the current strength in the
price of gold, the Company continues to evaluate the timing of the
Stage II hard rock expansion, which will further increase the gold
production profile at Bomboré to 225,000-250,000 ounces per
year.”
Engineering and Procurement
Lycopodium Minerals Canada (“Lycopodium”) was
awarded the engineering and procurement contract, and is
progressing ahead of schedule on both activities. Lycopodium was
selected for their successful track record of designing and
constructing numerous gold plants in West Africa, including the
Company’s oxide plant that is currently in operation and exceeding
nameplate design.
Engineering to end of December is at 52% versus
39% planned and all bulk quantities, including concrete, structural
steel and platework, remain in line with budget.
Overall, procurement is progressing better than
plan, with 82% of the total supply value now awarded. This includes
all mechanical equipment, long lead electrical equipment, and CIL
tank/general platework. The mill shells, heads, and ring gear, for
the 9MW 26’ diameter SAG mill, are en route and scheduled to arrive
to site early.
Site Construction
Activities
Construction of the hard rock expansion is ahead
of schedule, with the concrete contractor advancing major concrete
pours in multiple areas. Overall, concrete installation is three
months ahead of schedule, which will serve to provide multi-week
schedule flexibility as construction advances.
To date, all five CIL tank ring beams have been
poured, with the pedestal foundations for the trash screen and ore
bin installed. Foundations for the dump pocket and SAG mill are
advancing, with rebar installation for the dump pocket underway and
set to commence for the SAG mill shortly.
The SMP contract was recently awarded, with the
contractor scheduled to mobilize to site and commence the
installation of the CIL tanks in March.
The Company’s top priority remains the safety of
its employees and contractors. The Company is focused on
maintaining its leading safety record, which includes zero
lost-time injuries dating back to the start of construction of the
oxide plant in 2021.
Preparations for Hard Rock
Mining
The first delivery of the contractor’s hard rock
fleet, which includes new large-capacity trucks and excavators, was
placed into service in Q4-2024. This has allowed for systematic
training of operators well ahead of hard rock mining and has
facilitated more-cost effective mining of transition material in
the near-term. The remaining hard rock fleet will be delivered to
site in the coming months, in preparation of the ramp-up in hard
rock mining in late Q3-2025.
Construction of the explosives magazine is
complete and is now subject to final inspections and
certifications. Once in service, the Company will purchase and
store bulk explosives for mixing and preparation at site,
eliminating the need for the more costly pre-mix batch deliveries.
A full-service team from AECI, a world leader in the manufacture
and supply of explosives, will be onsite to mix and supply the
downhole explosives for blasting of transition and hard rock
material.
Further reducing mining costs are the two grade
control drill rigs purchased by the Company last year, which are
now fully operational. This eliminates the need for costly
contractor drilling, with this skill set now established in-house
in advance of the hard rock mining ramp-up later in the year.
Hard Rock Plant and Operations
Overview
The 2.5 million tonnes per annum (“Mtpa”) Stage
I hard rock expansion is designed to process higher-grade hard rock
ore. The expansion is independent of the adjacent 6.0Mtpa oxide
plant but will utilize a number of shared services and
infrastructure including the TSF, warehouses, administration
complex, and technical services. The concentrated scope of the
brownfield expansion significantly reduces schedule and budget risk
in comparison to a new build, with the ramp-up to benefit from the
well-established mining, processing, and maintenance teams
onsite.
The 2.5Mtpa Stage I hard rock expansion is
scheduled for commissioning in Q4-2025, which will see production
increase to over 170,000 ounces per year. As with the oxide plant,
which had a nameplate capacity of 5.2Mtpa, the Company views the
potential to achieve materially higher throughput rates than that
of the 2.5Mtpa Stage I design.
With the strong price of gold, the Company
continues to evaluate the timing of the Stage II hard rock
expansion, which will increase the nameplate hard rock throughput
to 5.0Mtpa, yielding a forecasted overall production profile of
225,000-250,000 ounces per year. With a 5.0Mtpa crusher to be
installed in Stage I, the Stage II expansion will primarily consist
of a ball mill, pebble crusher, thickener, four additional CIL
tanks and a gold room upgrade. Consideration in the Stage I design
and layout has been made to easily accommodate these Stage II
additions.
Figure 1: Bomboré Processing Complex –
Hard Rock Plant Layout (blue labels) Relative to Oxide Plant and
Other Established Infrastructure (white labels)
Figure 2: Dump Pocket/Jaw Crusher –
Rebar Installation for Raft Foundation
Figure 3: Installed CIL Ring Beams and
Trash Screen Pedestals
Figure 4: SAG Mill – Start of Raft
Foundation
About Orezone Gold
Corporation
Orezone Gold Corporation (TSX: ORE OTCQX: ORZCF)
is a West African gold producer engaged in mining, developing, and
exploring its flagship Bomboré Gold Mine in Burkina Faso. The
Bomboré mine achieved commercial production on its oxide operations
on December 1, 2022, and is now focused on its staged hard rock
expansion that is expected to materially increase annual and
life-of-mine gold production from the processing of hard rock
mineral reserves. Orezone is led by an experienced team focused on
social responsibility and sustainability with a proven track record
in project construction and operations, financings, capital markets
and M&A.
The technical report entitled Bomboré Phase II
Expansion, Definitive Feasibility Study is available on SEDAR+ and
the Company’s website.
Contact Information
Patrick DowneyPresident and Chief Executive
Officer
Vanessa PickeringManager, Investor Relations
Tel: 1 778 945 8977 / Toll Free: 1 888 673
0663info@orezone.com / www.orezone.com
For further information please contact
Orezone at +1 (778) 945-8977 or visit the Company’s
website at
www.orezone.com.
The Toronto Stock Exchange neither approves nor
disapproves the information contained in this news release.
Qualified Persons
The scientific and technical information in this
news release was reviewed and approved by Mr. Rob Henderson, P.
Eng, Vice-President of Technical Services and Mr. Dale Tweed, P.
Eng., Vice-President of Engineering, both of whom are Qualified
Persons as defined under NI 43-101 - Standards of Disclosure for
Mineral Projects.
Cautionary Note Regarding
Forward-Looking Statements
This press release contains certain information
that may constitute “forward-looking information” within the
meaning of applicable Canadian Securities laws and “forward-looking
statements” within the meaning of applicable U.S. securities laws
(together, “forward-looking statements”). Forward-looking
statements are frequently characterized by words such as
“plan”, “expect”, “project”, “intend”, “believe”, “anticipate”,
“estimate”, “potential”, “possible” and other similar words, or
statements that certain events or conditions “may”, “will”,
“could”, or “should” occur. Forward-looking statements
in this press release include, but are not limited to: the
construction of the Phase II Hard Rock expansion is ahead of
schedule and under budget; the hard rock expansion, which is
scheduled to commence operations in Q4-2025, is forecasted to
increase gold production by approximately 50%, to over 170,000
ounces per year; the Company continues to evaluate the timing of
the Stage II hard rock expansion, which will further increase the
gold production profile at Bomboré to 225,000-250,000 ounces per
year; the remaining hard rock fleet will be delivered to site in
the coming months, in preparation of the ramp-up in hard rock
mining in late Q3-2025; and the Company views the potential to
achieve materially higher throughput rates than that of the 2.5Mtpa
Stage I design.
All such forward-looking statements are based on
certain assumptions and analyses made by management in light of
their experience and perception of historical trends, current
conditions and expected future developments, as well as other
factors management and the qualified persons believe are
appropriate in the circumstances.
All forward-looking statements are subject to a
variety of risks and uncertainties and other factors that could
cause actual events or results to differ materially from those
projected in the forward-looking statements including, but not
limited to, delays caused by pandemics, terrorist or other violent
attacks (including cyber security attacks), the failure of parties
to contracts to honour contractual commitments, unexpected changes
in laws, rules or regulations, or their enforcement by applicable
authorities; social or labour unrest; changes in commodity prices;
unexpected failure or inadequacy of infrastructure, the possibility
of unanticipated costs and expenses, accidents and equipment
breakdowns, political risk, unanticipated changes in key management
personnel and general economic, market or business conditions, the
failure of exploration programs, including drilling programs, to
deliver anticipated results and the failure of ongoing and
uncertainties relating to the availability and costs of financing
needed in the future, and other factors described in the Company's
most recent annual information form and management discussion and
analysis filed on SEDAR+. Readers are cautioned not to place undue
reliance on forward-looking statements.
Although the forward-looking statements
contained in this press release are based upon what management of
the Company believes are reasonable assumptions, the Company cannot
assure investors that actual results will be consistent with these
forward-looking statements. These forward-looking statements are
made as of the date of this press release and are expressly
qualified in their entirety by this cautionary statement. Subject
to applicable securities laws, the Company does not assume any
obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this press release.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/59bc8c7a-cf26-4f6b-a365-9b85df0243fd
https://www.globenewswire.com/NewsRoom/AttachmentNg/e94a03d1-7871-4059-8154-b6be89da8afc
https://www.globenewswire.com/NewsRoom/AttachmentNg/a1da1217-e5ea-42ff-87a0-d01fb83ad08d
https://www.globenewswire.com/NewsRoom/AttachmentNg/1ee5da66-53da-46fb-bbc4-e3f84df924f3
Orezone Gold (TSX:ORE)
과거 데이터 주식 차트
부터 12월(12) 2024 으로 1월(1) 2025
Orezone Gold (TSX:ORE)
과거 데이터 주식 차트
부터 1월(1) 2024 으로 1월(1) 2025