Pentwater Issues Open Letter to Turquoise Hill Demanding Transparency and Accountability
02 11월 2021 - 10:00PM
Business Wire
Pentwater Capital Management LP ("Pentwater"), the
largest minority shareholder of Turquoise Hill Resources Ltd.
("Turquoise Hill") (TSX:TRQ) (NYSE:TRQ), has written the
attached letter to the TRQ Board of Directors:
Dear Members of the Board of Directors:
You have failed to disclose the damning findings of the
Independent Consulting Group (ICG) Report that TRQ itself
commissioned:
- “[Rio’s] lack of a comprehensive, overall project management
and project controls team, beginning during project preparation and
restart, is the fundamental reason for the project delay and cost
overruns.” (ICG Peer Report, p. 17)
- “The project began to fall behind schedule almost from the
beginning. The sinking (and commissioning) of Shafts #2 & #5
was critical to completing HNL1 on schedule. Shaft #2, critical to
support development and construction activities for the project,
was completed 461 days behind schedule. This caused a delay in the
mobilization of development crews, which is the fundamental reason
that mine development is behind schedule. The project team never
recovered from this delay.” (ICG Peer Report, p. 5)
- “It is inconceivable that Senior Management both on the
Project site and in the higher-level committees were not aware of
these shortcomings, as reports were generated on a regular basis by
the schedulers who were working in the Project Controls section and
by the relevant area managers. But there was also a culture on site
that did not welcome negative albeit actual, reporting.” (ICG
Report p. 92)
- “ICG does not consider ground support variances due to
design changes Key Geotechnical Parameter changes. The Rio Tinto
statement that these isolated poorer than expected ground
conditions significantly impacted the schedule is misleading and
not supported in the documents reviewed.” (ICG Report, p.
111).
- In August 2018, Rio Tinto had its consultant, Broadleaf,
conduct a range analysis of chances that the base date of 28 May
2021 for Sustainable Production “had a zero likelihood of being
achieved.” (ICG Report, p. 44).
These are some of the findings from the Independent Consulting
Group, the Experts1 hired by TRQ to investigate the cost overruns
and schedule delays at TRQ’s underground mine. You received this
157 page Independent Report and the companion Peer Review Report
(conducted by your own consultant John Barber and Rio’s former
block caving expert Allan Moss) over three months ago. However, in
those three months, you haven’t disclosed the report’s conclusions
or explained what TRQ intends to do in response to the results of
this Independent Report. Instead, all you have said is that you,
“will seek a number of clarifications and supporting detailed
explanations for certain of the broad conclusions [the ICG Report]
contains. The company will update the market as appropriate.”
Obviously, any owner of a part of the underground mine would be
very upset upon learning that Rio Tinto mismanaged the construction of the underground,
misled investors by not disclosing the
known and material schedule delays and cost overruns, and then
lied about the cause of the cost
overruns and schedule delays by fabricating a fictitious narrative
about adverse ground conditions. Any owner of the mine would want
transparency and accountability. Any owner of the mine would want
to hold its contractor, Rio Tinto, accountable. Unfortunately for
TRQ’s minority investors, they are represented by Rio’s hand-picked
Board of Directors.
The Independent Report concludes that geotechnical issues did
not significantly impact the mine schedule or explain over 95% of
the cost overruns. Why does TRQ continue to remain silent on this
issue? Why is the TRQ Board not aggressively pursuing its reckless
and dishonest contractor, Rio Tinto? You said that you intended to,
“update the market as appropriate.” Since you plan to come out with
earnings this afternoon and have an analyst call tomorrow morning,
I would suggest to you that NOW is the appropriate time to update
the market about your response to the Independent Report, given
your failure to do so for the past three months.
Your lack of transparency to minority shareholders is the worst
I have seen in my career. Your efforts to protect Rio Tinto, your
majority shareholder, to the detriment of your minority
shareholders is scandalous. Your failure to allow minority
shareholder representation on the TRQ board is a complete failure
of corporate governance. Asking for your former CEO’s resignation
because he was willing to investigate the cost overruns rather than
sweep them under the rug is corrupt.
As a result of Rio’s mismanagement of the construction of the
underground mine and Rio’s fabricated story about poor ground
conditions, the government of Mongolia is seeking financial
restitution so that it is compensated for its 34% share of the
financial losses associated with the cost overruns and schedule
delays. This is a logical course of action, and TRQ should also be
looking to Rio Tinto for financial reparations for Rio’s
mismanagement of the underground construction. Instead, if history
is any guide, Rio Tinto will utilize its control over TRQ to
attempt to get TRQ to compensate the government of Mongolia for
harm caused by Rio Tinto, rather than Rio compensating both the
Government and TRQ’s minority shareholders. Should this be your
plan, I sincerely hope that your D&O liability insurance is
paid in full because it is difficult to understand how minority
investors won’t take decisive action in these circumstances.
You owe a duty to your shareholders to immediately:
- Disclose the conclusions from the Independent Report and how
TRQ intends to address them.
- Disclose the portions of the Independent Report that you
agree with or disagree with and your reasoning for such agreement
or disagreement.
- Disclose in detail how the cash needs for the underground
mine changed so materially between July 29, 2021 and October 14,
2021.
- Disclose whether you intend to take appropriate action to
hold Rio Tinto accountable for its mismanagement of the underground
construction of the mine.
- Disclose affirmatively that any reparations made to the
government of Mongolia will be paid for by the responsible party
Rio Tinto rather than by TRQ.
It is never too late to do the right thing. Please begin by
making honest and complete disclosures to your minority
shareholders. Then start making decisions which have the effect of
treating all your shareholders fairly. If you cannot fulfill these
basic fiduciary obligations to your minority shareholders, I
suggest that you all resign.
Pentwater continues to hope that you will change course and do
the right thing.
Regards,
Matthew Halbower Chief Executive Officer Pentwater Capital
Management
1 Five of the eight independent consultants behind the ICG’s
Final Report worked directly on the Oyu Tolgoi project for Rio
Tinto and TRQ.
- Lead Consultant Chris Beaumont who has 15 years of experience
at Rio Tinto, including 5 years specifically at Oyu Tolgoi.
- Zarex Robas worked for Rio at Oyu Tolgoi for 7 years,
specializing in Procurement and Contracts
- Sim Lau was a Project Services General Manager for TRQ and
seconded to OT up until 2014
- Monica Bernard served as Commercial Manager at Oyu Tolgoi,
specializing in project and construction management
- Malcolm Brown is a mining consultant with 30+ years of
experience, including working on Oyu Tolgoi
View source
version on businesswire.com: https://www.businesswire.com/news/home/20211102005811/en/
David Zirin- Chief Operating Officer Pentwater Capital
Management 312-589-6401
Turquoise Hill Resources (TSX:TRQ)
과거 데이터 주식 차트
부터 10월(10) 2024 으로 11월(11) 2024
Turquoise Hill Resources (TSX:TRQ)
과거 데이터 주식 차트
부터 11월(11) 2023 으로 11월(11) 2024