Endeavour Silver Provides Q3 Construction Update on the Terronera Project; Construction Progress is Nearing 40%
26 10월 2023 - 7:50PM
Endeavour Silver Corp.
(“Endeavour” or the
“Company”) (NYSE: EXK; TSX: EDR) is
pleased to provide a Q3 construction update for its Terronera
Project in Jalisco state, Mexico. The photo gallery presentation
which accompanies this news release can be found
here or on the Company website at
Terronera Project Progress Photos. All dollar ($)
references in this news release are United States dollars.
“During Q3, we’ve made notable progress in a
number of key areas,” commented Don Gray, Chief Operating Officer.
“Not only have we completed construction of our permanent camp and
can now fully accommodate our workforce, but we’ve also made
significant progress on construction of our process plant. Our
procurement efforts are on schedule, with most long-lead major
equipment anticipated to be received by year’s end. With our
underground mine development, we’re seeing a noticeable increase in
rates, as our mining team is now advancing four working faces
simultaneously. We’re pleased with Terronera’s progress to date as
we expedite completion of this next core asset.”
Q3 2023 Construction and Development
Highlights
Early works, initiated in the first quarter of
2022, have rapidly advanced, with more than $95 million of the
project’s budget spent to date. Overall construction progress is
38% complete. Project commitments total $160 million, which is 69%
of the $230.4 million capital budget. The project remains on track
and on budget for initial production in Q4 2024. As of September
30, 2023, site works and activities have included:
- Safety – Our strong safety focus at
site continues. Key safety initiatives have included improved
accident investigation procedures, accident prevention measures,
and development of on-site emergency brigade. During the recent
annual rainy season, hazard lightning control measures were
reinforced.
- Engineering – Total engineering
progress is 97% complete. The mine waste rock dump design is
nearing completion. Final design for the tailing storage facility
as well as the filters, LNG and warehouse areas is pending
completion of geotechnical site investigation.
- Access Road Construction –Site road
access is now established following extensive improvements over the
last year. Equipment access and material deliveries to site
remained unaffected during the annual rainy season.
- Permanent Camp – All permanent camp
dormitory units have been installed for accommodation of 550
personnel. Fully operational facilities include the dining,
laundry, medical clinic, and training areas.
- Mine Development – During Q3,
Portal 1 mine yard excavation reached the design elevation of 1,475
metres allowing mine development to advance on four fronts: Portal
1, Portal 2, and Portal 4 (incline & decline). Over 1,300
metres of underground development have been completed through to
Q3. As planned, mining advance rates increased as Portals 2 and 4
passed through the fault zone and ground conditions improved.
- Plant Site – Concrete work and
rebar installation continued in the SAG and ball mill grinding,
coarse ore stockpile and flotation areas, and concrete work began
for the primary crusher. Excavation work started in the tailing
thickener area.
- Procurement – Most long-lead major
equipment is anticipated to be received by year’s end. Purchase
order contracts were executed for initial structural steel support.
During Q3, the request for bid proposal for the mill construction
contract was released, which includes structural steel, mechanical,
piping, electrical and instrumentation.
- Onsite Personnel – The workforce
has increased to 91 employees and 430 contractor workers.
- Community Relations – During Q3, community relations focused on
local municipality support to maintain and improve municipal roads
from the state highway to the site area, as well as assistance with
a municipal landfill facility. Additionally, local community
suppliers continued to be integrated into the Terronera value
chain. Summer initiatives included several cultural and sports
activities.
- Environmental – Environmental and
social assessment initiatives continued as outlined under the
Equator Principal requirements set forth within the project loan
financing. Items completed during Q3 included the flora and fauna
baseline study, integrated pest management plan, rainy season
biodiversity monitoring, and the visual baseline report. In
addition, development of a comprehensive reclamation and closure
program is in progress.
- Liquidity – Upon execution of a
credit agreement for a $120 million senior secured debt facility,
the Company is well-positioned to satisfy the financing
requirements of the project (see news release dated October 10,
2023). It is expected that Project commitments will total nearly
100% of the $230.4 million budget in early Q2 2024.
Project Timeline and Next
Steps
The Company remains focused on advancing the
Terronera Project to initial production. Upcoming major milestones
include:
- Advancing mill area concrete work
on schedule with the electromechanical contractor mobilization
schedule; handover in early 2024.
- Electromechanical contract award
and mobilization – Q4 2023.
- Waste Dump area two earthworks – Q4
2023.
- Begin filtration and LNG power
plant area platform excavation – Q4 2023.
- Complete Portal 4 incline
breakthrough to surface – Q4 2023.
- Develop Portal 2 and Portal 4
declines for initial ore access – Q1 2024.
- Continue developing Portal 1
decline to establish main haulage and lower ore access.
About Endeavour Silver –
Endeavour is a mid-tier precious metals mining company that
operates two high-grade underground silver-gold mines in Mexico.
Endeavour is advancing construction of the Terronera Project and
exploring its portfolio of exploration projects in Mexico, Chile
and the United States to facilitate its goal to become a premier
senior silver producer. Our philosophy of corporate social
integrity creates value for all stakeholders.
Contact InformationGalina Meleger, VP, Investor
RelationsEmail: gmeleger@edrsilver.comWebsite:
www.edrsilver.com
Follow Endeavour Silver on Facebook, Twitter,
Instagram and LinkedIn.
Cautionary Note Regarding
Forward-Looking Statements
This news release contains “forward-looking
statements” within the meaning of the United States private
securities litigation reform act of 1995 and “forward-looking
information” within the meaning of applicable Canadian securities
legislation. Such forward-looking statements and information herein
include but are not limited to statements regarding the development
and financing of the Terronera Project, including: anticipated
timing of the Project, anticipated timing of and completion of
conditions precedent to drawdown under the Debt Facility, estimated
project economics, Terronera’s forecasted operations, costs and
expenditures, and the timing and results of various activities. The
Company does not intend to and does not assume any obligation to
update such forward-looking statements or information, other than
as required by applicable law.
Forward-looking statements or information
involve known and unknown risks, uncertainties and other factors
that may cause the actual results, level of activity, production
levels, performance or achievements of Endeavour and its operations
to be materially different from those expressed or implied by such
statements. Such factors include but are not limited to the
completion of conditions precedent to drawdown under the Debt
Facility; the ongoing effects of inflation and supply chain issues
on Project economics; national and local governments, legislation,
taxation, controls, regulations and political or economic
developments in Canada and Mexico; financial risks due to precious
metals prices; operating or technical difficulties in mineral
exploration, development and mining activities; risks and hazards
of mineral exploration, development and mining; the speculative
nature of mineral exploration and development; risks in obtaining
necessary licenses and permits; and challenges to the Company’s
title to properties; as well as those factors described in the
section “risk factors” contained in the Company’s most recent form
40F/Annual Information Form filed with the S.E.C. and Canadian
securities regulatory authorities.
Forward-looking statements are based on
assumptions management believes to be reasonable, including but not
limited to: the ability of the Company to satisfy conditions
precedent to drawdown under the Debt Facility, Terronera’s
forecasted operations, costs and expenditures, and the timing and
results of various activities, the continued operation of the
Company’s mining operations, no material adverse change in the
market price of commodities, the Project’s forecasted economics as
of 2023, mining operations will operate and the mining products
will be completed in accordance with management’s expectations and
achieve their stated production outcomes, and such other
assumptions and factors as set out therein. Although the Company
has attempted to identify important factors that could cause actual
results to differ materially from those contained in
forward-looking statements or information, there may be other
factors that cause results to be materially different from those
anticipated, described, estimated, assessed or intended. There can
be no assurance that any forward-looking statements or information
will prove to be accurate as actual results and future events could
differ materially from those anticipated in such statements or
information. Accordingly, readers should not place undue reliance
on forward-looking statements or information.
Endeavour Silver (TSX:EDR)
과거 데이터 주식 차트
부터 10월(10) 2024 으로 11월(11) 2024
Endeavour Silver (TSX:EDR)
과거 데이터 주식 차트
부터 11월(11) 2023 으로 11월(11) 2024