Continental Gold Provides Construction Update
11 4월 2018 - 6:18AM
Continental Gold Inc. (TSX:CNL) (OTCQX:CGOOF)
(“Continental” or the “Company”) is pleased to provide a
construction update for its Buriticá project in northwestern
Antioquia, Colombia (please see accompanying photos). Construction
completion and first gold pour remain on schedule for H1 2020, with
commercial production ramp-up anticipated approximately six months
after first gold pour.
The Buriticá project is approximately 25%
complete with more than 40% of the total project cost committed to
date. The Company continues to be well-financed with available
liquidity of approximately US$262 million as of March 31, 2018.
Major earthworks continue, with completion
scheduled for Q4 2018. The concrete contract has been awarded and
the contractor has mobilized and set up operations in the Higabra
valley. Concrete placement for the mill foundations is expected to
begin this week, followed by concrete for tailing filters and leach
circuit in the coming weeks. Mill and surface infrastructure detail
engineering and procurement are moving forward on schedule;
progress is more than 75% complete as of March 31, 2018.
The access road into the Higabra valley was
completed earlier this year and is in use by large transport trucks
for equipment deliveries. Fabrication of major mill components
continues and shipments are beginning to arrive in‑country.
Building fabrication and installation is ongoing and structural
steel fabrication has commenced with erection expected to begin in
Q3 2018. Other major contracts — including the general contract for
installing steel, mechanical, piping, electrical and
instrumentation — and the tailing facility construction are
expected to be awarded by the end of Q2 2018.
Underground development continues on schedule
with advance rates increasing as development crews undergo training
and become more efficient. As of March 31, 2018, 2,400 metres of
underground development has been completed with advance moving
forward on three different fronts: the Yaraguá ramp, the Veta Sur
ramp and the Higabra tunnel. Major mobile equipment has been
arriving to site in accordance with the development ramp-up
schedule, including 4 jumbos; 3 rock bolters; 8 underground trucks;
3 LHDs and 16 utility vehicles to date. The current underground
fleet includes more than 70% of mobile equipment required for
production startup.
The Company continues to seek out and employ
local talent and is providing mechanized mining training to these
workers. As of March 31, 2018, 82% of the Company’s workforce were
from the department of Antioquia with 56% from local municipalities
within the Buriticá project’s influence area.
“This is an exciting time for the Buriticá
project,” commented Donald Gray, Chief Operating Officer.
“Construction activities are moving forward rapidly and the project
continues to meet our construction schedule targets. We are truly
witnessing the transformation of the Higabra valley into a modern
mine site. Underground development rates are also meeting
expectations as ramp-up continues. We remain strongly focused on
maintaining our construction and development schedule, ensuring we
achieve our health and safety objectives and delivering on our
strong commitment to building Colombia’s largest and most modern
underground gold mine.”
About Continental Gold
Continental Gold Inc. is an advanced-stage
exploration and development company with an extensive portfolio of
100%-owned gold projects in Colombia. Formed in April 2007, the
Company – led by an international management team with a successful
track record of discovering and developing large high-grade gold
deposits in Latin America – is focused on advancing its
fully-permitted high-grade Buriticá gold project to production with
first gold pour on track for early 2020.
For information on the Buriticá project, please
refer to the technical report, prepared in accordance with NI
43–101, entitled “Buriticá Project NI 43–101 Technical Report
Feasibility Study, Antioquia, Colombia” and dated March 29, 2016
with an effective date of February 24, 2016, led by independent
consultants JDS Energy & Mining Inc. The technical report is
available on SEDAR at www.sedar.com, on the OTCQX at
www.otcmarkets.com and on the Company website at
www.continentalgold.com. Additional details on Continental Gold’s
suite of gold exploration properties are also available at
www.continentalgold.com.
For further information, please
contact:
Paul BeginChief Financial OfficerContinental
Gold Inc.+1.416.583.5610info@continentalgold.com
www.continentalgold.com
Forward-Looking Statements
This news release contains or refers to
forward–looking information under Canadian securities legislation,
including statements regarding the development and construction of
the Buriticá project, completion of various construction and
development activities, expected delivery of underground mining
development and drilling equipment, ramp-up of underground
development activities, timing of production start-up, advancing
the Buriticá project and future plans and objectives of the
Company, and is based on current expectations that involve a number
of significant business risks and uncertainties. Forward–looking
statements are subject to other factors that could cause actual
results to differ materially from expected results. Readers should
not place undue reliance on forward–looking statements. Factors
that could cause actual results to differ materially from any
forward–looking statement include, but are not limited to, an
inability to advance the Buriticá project to the next level,
failure to convert estimated mineral resources to reserves, capital
and operating costs varying significantly from estimates, the
preliminary nature of metallurgical test results, delays in
obtaining or failures to obtain required governmental,
environmental or other project approvals, political risks,
uncertainties relating to the availability and costs of financing
needed in the future, changes in equity markets, inflation, changes
in exchange rates, fluctuations in commodity prices, delays in the
development of projects and the other risks involved in the mineral
exploration and development industry. Specific reference is made to
the most recent Annual Information Form on file with Canadian
provincial securities regulatory authorities for a discussion of
some of the factors underlying forward–looking statements. All the
forward–looking statements made in this news release are qualified
by these cautionary statements, and are made as of the date hereof.
The Company assumes no responsibility to update them or revise them
to reflect new events or circumstances other than as required by
law.
Collective Mining (TSX:CNL)
과거 데이터 주식 차트
부터 10월(10) 2024 으로 11월(11) 2024
Collective Mining (TSX:CNL)
과거 데이터 주식 차트
부터 11월(11) 2023 으로 11월(11) 2024