Beatons Creek Operational Update
18 12월 2020 - 12:18AM
Novo Resources Corp. (“
Novo” or
the “
Company”) (TSX-V: NVO & NVO.WT; OTCQX:
NSRPF) is pleased to provide an operational update from its Beatons
Creek gold project (“
Beatons Creek”) and Nullagine
processing facility (
“Golden Eagle Mill”).
Beatons Creek and Nullagine Gold Project
Update:
Development at Beatons Creek and refurbishment at
the Golden Eagle Mill continue to progress safely, on schedule and
within budget. Recent key events and milestones include:
- Iron Mine Contracting Pty Ltd
(“IMCPL”) has commenced ramping up activities from
today;
- 1 in 500 year rain event on Dec
11th and 12th (320mm in 48 hours) caused flooding in the town of
Nullagine and some damage to the haulage route and communications.
Site access and regional communications were re-established without
impacting project schedule;
- Haulage of material to the Golden
Eagle Mill will commence from 21st December once the main Newman to
Marble Bar road is satisfactorily repaired;
- As a result of the recent rain
event, the site now has in excess of 6 months water supply in the
Golden Eagle pit adjacent to the plant to complement the site
borefield supply;
- Site is preparing for a scheduled
holiday hiatus in processing plant construction activities from
22nd December until 4th January; and
- Site personnel (including
contractors) now total 90.
Please see the Company’s news release dated
December 8, 2020 for the Company’s previous operational update.
Development activities at Beatons
Creek:
- IMCPL and Edwards Earthmoving P/L
continuing with mining development works;
- IMCPL Mining equipment mobilized to
site includes 1 x D10 dozer, 1 x PC850 excavator, CAT 740B
watercart, 14M grader and 3 x CAT 745 trucks, with additional fleet
scheduled to arrive within a week (see figure 1 and figure 2
below);
- Lacy Contracting Services P/L are
preparing to commence haulage from Beatons Creek to the Golden
Eagle Mill from 21st December;
- Grade control reverse circulation
drilling by Castle Drilling continues on two shifts across the
Edwards and Grant’s Hill areas, with this initial grade control
program schedule for completion by 22nd December;
- Beatons Creek ROM pad has been
widened;
- Topsoil stripping of Grant’s Hill
waste dump location has been completed; and
- Office buildings have been
relocated from the Golden Eagle Mill to Beatons Creek (see figure 3
below).
Refurbishment works on the Golden Eagle
Mill:
Plant refurbishment:
- The GR Engineering Services
(“GRES”) scope currently stands at approximately
60% complete, with works continuing on schedule and within budget
with no material issues or problems encountered thus far;
- Works continue with refurbished key
componentry returning from Perth for installation – all continues
according to schedule;
- Preparation and painting of the
tanks will be completed prior to Christmas with only the inter-tank
launders remaining to be painted in the first working week of
January;
- Gravity section steelwork erection
continues ahead of receipt and installation of the upgraded gravity
circuit components;
- All long lead items have been
ordered, with arrival dates remaining within the project schedule;
and
- Commissioning planning is well
advanced and on schedule.
Civil works:
- Foundations have now been completed
for the upgraded Acacia reactor unit and new elution tank footings
in the gold room.
Other major tenders:
- The permanent surface haulage
contract package is currently out for tender, with solid progress
being made with numerous other commercial agreements for fuel
supply, processing reagents, and flights.
Novo CEO and director Rob Humphryson commented,
“Despite the challenges created by some recent heavy rainfall, the
project is tracking safely, within budget and to schedule. All
contractors at the site continue to perform outstanding work and we
thank them for their cooperative efforts.”
Dr. Quinton Hennigh (P.Geo.) is the qualified
person pursuant to NI 43-101 responsible for, and having reviewed
and approved, the technical information contained in this news
release. Dr. Hennigh is President, Chairman, and a director of
Novo.
About Novo Resources Corp.
Novo is advancing its flagship Beatons Creek
gold project to production while exploring and developing its
highly prospective land package covering approximately 14,000
square kilometres in the Pilbara region of Western Australia. In
addition to the Company’s primary focus, Novo seeks to leverage its
internal geological expertise to deliver value-accretive
opportunities to its shareholders. For more information, please
contact Leo Karabelas at (416) 543-3120 or
e-mail leo@novoresources.com
On Behalf of the Board of Directors,
Novo Resources Corp.
“Quinton Hennigh”Quinton Hennigh President and
Chairman
Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.
Forward-looking information
Some statements in this news release contain
forward-looking information (within the meaning of Canadian
securities legislation) including, without limitation, the
successful completion of development and plant refurbishments works
on time and on budget, and that Novo’s board of directors will make
the decision to commence full-scale production at Beatons Creek.
Forward-looking statements address future events and conditions
and, as such, involve known and unknown risks, uncertainties and
other factors which may cause the actual results, performance or
achievements to be materially different from any future results,
performance or achievements expressed or implied by the statements.
Such factors include, without limitation, the successful completion
of site establishment works at Beatons Creek, the successful
completion of grade control drilling works, the successful
completion of mining, camp management, fuel supply, processing
reagents, assay laboratory services, flights, and haulage services
contracts, and customary risks of the resource industry.
PDFs accompanying this announcement are
available at:
http://ml.globenewswire.com/Resource/Download/7a85f865-47a5-4657-aa34-34a59f6ca8c8
http://ml.globenewswire.com/Resource/Download/f8c3f956-a532-48cf-bf08-14d546fdfb60
http://ml.globenewswire.com/Resource/Download/3ab0ce66-65eb-4cb7-b07a-6511654c2acb
Novo Resources (TSXV:NVO)
과거 데이터 주식 차트
부터 10월(10) 2024 으로 11월(11) 2024
Novo Resources (TSXV:NVO)
과거 데이터 주식 차트
부터 11월(11) 2023 으로 11월(11) 2024