Project and Production Update (9560Y)
08 3월 2012 - 7:38PM
UK Regulatory
TIDMANGM
RNS Number : 9560Y
Angel Mining PLC
08 March 2012
ANGEL MINING PLC
("Angel Mining" or the "Company")
AIM: ANGM
Project and Production Update
The Company has continued to make good progress at the Nalunaq
Gold Mine towards reaching its target production range of 1,500 to
2,000 ounces of gold dore per month. The mine has been successfully
producing high grade ore and the process plant has been recovering
approximately 85% of gold from the feed material.
There were 2 gold pours in January totalling 32.9kg (approx. 952
ounces of saleable gold) and the latest pour on 28 February was
16.945kg (approx. 490 ounces of saleable gold).
Production in February was less than expected due to the failure
of a critical pump in the process plant which put the plant out of
commission while replacement parts were sourced, delivered to
Greenland and installed. In total the failure resulted in 10 days
of downtime. The failure of the pump was progressive and was due to
the abrasive nature of the host rock. The rate of wear was much
faster than had been anticipated and, in consequence, the company
has now purchased a standby pump and increased its inventory of
spares.
March production was expected to exceed the lower level of the
target range of 1,500 ounces. However, unfortunately the company
suffered a further setback on the 6(th) of March when the main
generator lost a piston, causing terminal damage to the engine
block. The main generator, in addition to providing power for the
mine and support facilities, also powers the processing plant
including the front end crushing circuit. Currently, Nalunaq is
using the standby generator, which is able to support the mining
operation and the process plant but it is not powerful enough to
drive the front end crushing circuit. As a result, there will be
further disruption to the gold output during March, although it is
estimated that there is sufficient ore already part processed to
produce approximately 15kg of dore by mid March.
A replacement engine is being supplied by the Caterpillar dealer
in Denmark and it should be on site by 23(rd) March. It is likely
to take 2 or 3 days to commission the engine once it is delivered,
so gold processing should recommence a few days before month end.
Mining will continue during this period and the ore will be
stockpiled until there is sufficient power to run the crushing
circuit. In addition, the company will also commission the final
process plant upgrade during this period which should increase the
recovery rate at the plant to its final target level of
approximately 90%.
During the time when the full capabilities of the mill will be
unavailable, the management team is doing what it can to reduce
short term costs and is rescheduling periods of leave for employees
who are not needed during the maintenance and upgrade period.
The shutdown will have an inevitable impact on working capital
and liquidity and the Company is working with its operational and
financial creditors to ensure that it has competent payment
agreements which can be upheld. The Company also has the continued
support of its other financial creditors who are working
constructively with the company to allow it to reach its target
production levels and meet its financial commitments as they fall
due.
Nicholas Hall, CEO, commented: "I have been delighted with the
way in which our team at Nalunaq has been strengthened in the last
year and, having just been on site, I can confirm that spirits and
confidence are high. The setback in February was very frustrating
but it demonstrates how very important it is, when working in
Greenland, to make sure that we are vigilant about maintenance and
overhaul of all of our equipment. We cannot simply drive to the
supplier and pick up the right part if it is not available in our
own stores. However, we have the high grade ore and we have a plant
that works and a competent team, so our next news release should be
much more encouraging for shareholders. To put this latest setback
into perspective, we are likely to lose three weeks of ore crushing
but otherwise the mining operations are running well and building
towards our target"
Enquiries:
Angel Mining plc
Nicholas Hall, Chief Executive Officer 07931 709 053
Kevin McNair, Chief Financial Officer 07900 690 908
Enquiries:
Angel Mining plc
Nicholas Hall, Chief Executive
Officer 07931 709 053
Kevin McNair, Chief Financial
Officer 07900 690 908
Fox-Davies Capital (Broker)
Daniel Fox-Davies
Simon Leathers 0203 463 5010
Fox-Davies (Nominated Adviser)
Simon Leathers 0203 463 5010
Bishopsgate Communications Limited
Nick Rome/Shabnam Bashir 0207 562 3350
This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLBVLFBLXFXBBX
Angel Mining (LSE:ANGM)
과거 데이터 주식 차트
부터 12월(12) 2024 으로 1월(1) 2025
Angel Mining (LSE:ANGM)
과거 데이터 주식 차트
부터 1월(1) 2024 으로 1월(1) 2025