Argonaut Gold Inc. ("Argonaut Gold" or the "Company") (TSX:AR), announced today
that the Company produced 16,884 ounces of gold during the 3rd quarter of 2011
(ended September 30, 2011) at its 100% owned El Castillo Mine ("El Castillo"),
located 100 km north of the city of Durango, Mexico.  


THIRD QUARTER 2011 HIGHLIGHTS: 

Operations



--  Continued greater than 1.5 million total tonnes mined per month 
--  29,997 ounces loaded on the pad, 24% increase over Q3 2010 
--  Gold production of 16,884 ounces, 33% increase over Q3 2010 
--  Finalized agreement with the Company's mining contractor to expand the
    mining fleet from 13 to 16 trucks with 100 tonne capacity 
    --  Two additional trucks on site in October 
    --  One additional truck and one loader to be added into production in
        November 
--  Finalized an agreement expanding surface rights on the western side of
    the property by 100 hectares, for an increase in overall surface rights
    to 1385 hectares. 



El Castillo East Side Expansion Program



--  West crusher relocated to east side for consolidated crushing circuit
    with design capacity of 500,000 tonnes per month ("TPM") 
--  East side pad loading initiated and east carbon plant operational in
    October with the ramp up to continue thru Q4 of 2011  



2011 Project Highlights 



--  El Castillo - 1,800 metre core drill program completed to obtain
    sulphide samples for metallurgical test work 
--  San Antonio - Advancements made on land and water purchases, as well as
    significant progress on environmental studies 
    --  10,242 metres of drilling complete across 71 holes 
    --  Ongoing drill programs with 2 drill rigs running 
        (1 exploration and 1 metallurgical) 

--  La Colorado - 52,000 metre drill program continues 
    --  33,214 metres complete across 195 holes 
    --  Ongoing drill program with 3 drill rigs running 
        (2 core and 1 reverse circulation drill) 
    --  Resource report by SRK & Associates of Denver expected by the end of
        October 



THIRD QUARTER 2011 OPERATING RESULTS: 

The third quarter operating statistics showed improvement over the prior year as
well as year to date. Ore production has continued at an annualized rate of more
than 11 million tonnes. The west side crusher was disassembled and relocated on
the east side of the property to provide a centralized crushing facility with a
capacity of 500,000 TPM. The east pad and the east side carbon plant (a
duplicate plant of the west side facility with a name plate capacity of 500,000
TPM capacity) were commissioned in October. Production is still expected to
finish the year at approximately 70-75,000 ounces with a $575-$600 cash cost. 


Recovery rate was 56% for the quarter, up from the prior year's rate of 53% but
slightly lower than last quarter. This was a result of higher stacking lifts,
downtime associated with moving the crusher and some cyanide shortages at the
beginning of the quarter. (Recovery rate is defined as ounces produced over
ounces loaded to pads.) 


During Q3 of 2011, 13,260 ounces of gold were sold. At September 30, 2011, a
large inventory of approximately 6,200 gold ounces from Q3 were on hand and had
not been sold, primarily due to volatility in the gold price. The Company sold
6,192 of these ounces in October at an average price of $1,658 per ounce, or
roughly $10 million additional cash. 




                                El Castillo Operating Statistics            
                                                                            
                    3 Months Ended September 30  9 Months Ended September 30
                                              %                            %
                          2011      2010 Change       2011       2010 Change
                    --------------------------------------------------------
Mining                                                                      
--------------------                                                        
Total tonnes mined   4,841,620 4,749,610    +2% 14,571,913 11,093,516   +31%
Tonnes ore mined     2,908,150 2,013,668   +44%  8,232,763  5,197,406   +58%
Heap Leach Pad                                                              
--------------------                                                        
Direct ore tonnes to                                                        
 pad                 2,282,601 1,675,504   +36%  6,016,269  4,237,532   +42%
Crushed ore tonnes                                                          
 to pad                612,548   369,275   +66%  2,201,941    954,559  +131%
Production                                                                  
--------------------                                                        
Gold grade (g/t)          0.32      0.37   -14%       0.33       0.37   -11%
Gold loaded to pad                                                          
 (oz)                   29,997    24,202   +24%     87,777     60,744   +45%
Gold loaded to                                                              
 carbon (oz)            16,884    12,724   +33%     52,351     33,032   +59%
Gold sold               13,260     7,994   +66%     46,052     26,779   +72%
(1) "g/t" is grams per tonne                                                
(2) "oz" means ounce                                                        



Pete Dougherty, President and CEO of Argonaut Gold noted: "Quarterly gold
production provided meaningful ounces towards our guidance for the year and was
slightly impacted by the pad height on the west pad, cyanide availability and
the relocation of the crushing circuit to the east side. To date 2011 has shown
great promise for Argonaut Gold; key initiatives were completed to provide
flexibility in our production profile with the commissioning of the east side
plant, construction of heap leach pads, adding new equipment to the mining fleet
and finally expanding our land position by 100 hectares to the west." 


About Argonaut Gold 

Argonaut Gold is a Canadian gold company engaged in exploration, mine
development and production activities. Its primary assets are the
production-stage El Castillo Mine in the State of Durango, Mexico, the advanced
exploration stage San Antonio project, the past producing and advanced
exploration stage La Colorada project, and several exploration stage projects,
all of which are located in Mexico. 


Creating Value Beyond Gold 

Cautionary Note Regarding Forward-looking Statements

This news release contains forward-looking statements that involve risks and
uncertainties that could cause results to differ materially from management's
current expectations. Actual results may differ materially due to a number of
factors. Except as required by law, Argonaut Gold Inc. assumes no obligation to
update the forward-looking information contained in this news release. 


Qualified Person 

Preparation of this release was supervised by Thomas Burkhart, Argonaut Gold's
Vice President of Exploration, and a Qualified Person under NI 43-101. For
additional information on El Castillo please refer to the "NI 43-101 Technical
Report on Resources and Reserves, Argonaut Gold Inc., El Castillo Mine, Durango
State, Mexico" dated Nov. 6, 2010 and available at Argonaut Gold's website and
profile on www.sedar.com.


Argonaut Gold (TSX:AR)
과거 데이터 주식 차트
부터 6월(6) 2024 으로 7월(7) 2024 Argonaut Gold 차트를 더 보려면 여기를 클릭.
Argonaut Gold (TSX:AR)
과거 데이터 주식 차트
부터 7월(7) 2023 으로 7월(7) 2024 Argonaut Gold 차트를 더 보려면 여기를 클릭.