Ascot Resources Ltd. (
TSX: AOT; OTCQX:
AOTVF) (“
Ascot” or the
“
Company”) is pleased to announce the Company’s
unaudited financial results for the three and nine months ended
September 30, 2023 (“
Q3 2023”), and also to
provide a construction update on the Company’s Premier Gold Project
(“
PGP” or the “
project”), located
on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of
northwestern British Columbia. For details of the unaudited
condensed interim consolidated financial statements and
Management's Discussion and Analysis for the three and nine months
ended September 30, 2023, please see the Company’s filings at
www.ascotgold.com or on SEDAR+ (www.sedarplus.ca).
Derek White, President and CEO, commented, "The
third quarter was the busiest yet for construction activity at the
Premier Gold Project, with much progress being made on outdoor
areas such as the tailings storage facility earthworks, the new
water treatment plant, and the electrical substation. We continue
to show excellent safety performance with zero lost time injuries
and with a new quarterly record-low recordable incident
frequency.
Underground development and ore stockpiling has
resumed at the Big Missouri deposit, coinciding well with
record-high gold grades recently intercepted from drilling in that
deposit. Additionally, the surface work has been completed for the
new Premier portal, and underground development will commence
shortly and advance towards the Prew Zone by early 2024, which will
enable Ascot to source production from two portals when milling
operations commence.
The 2023 exploration program has been very
successful so far in achieving both short- and long-term goals.
In-fill drilling at the Prew Zone of the Premier deposit, and at
Big Missouri, has yielded plenty of high-grade gold intercepts in
and around planned stopes. For the long-term, our IP geophysics
program this year provided promising targets for future step-out
drilling across many areas.”
All amounts herein are reported in $000s of
Canadian dollars (“C$”) unless otherwise
specified.
Q3 2023 AND RECENT
HIGHLIGHTS
- At the end of Q3 2023, overall construction excluding mine
development was 66% complete (73% as of October 31, 2023), compared
with 48% complete at the end of Q2 2023. Detailed engineering and
procurement are substantially complete. The Company anticipates the
first gold pour by the end of Q1 2024.
- On August 8, 2023, the Company entered into a contract with
Procon Mining & Tunnelling Ltd. for underground mining services
for an initial term of three years with the Company having the
option to renew for two consecutive one-year periods. In August
2023, excavation work commenced on the new Premier portal close to
the mill, including establishing the start of an access road for
waste disposal in the historic Premier pit. Dewatering of the
existing Big Missouri development and re-establishing surface
infrastructure also commenced in August.
- The Company’s 2023 exploration program at PGP consisted of 88
holes totaling 11,886 metres and included exploration drilling for
resource expansion as well as in-fill drilling of initial mining
areas at the Big Missouri and Premier deposits. On August 25, 2023,
the Company announced the first batch of assay results with
highlights including 32.85 g/t Au and 216.18 g/t Ag over 4.90m from
a depth of 273.1m in hole P23-2468 and 54.28 g/t Ag over 6.52m from
a depth of 253.48m in hole P23-2465. On October 19, 2023, the
Company announced the second batch of assay results with highlights
including 18.93 g/t Au over 6.87m from a depth of 278.1m in hole
P23-2475 and 21.98 g/t Au over 4.28m from a depth of 279.2m in hole
P23-2472. On November 3, 2023, a third batch of assay results was
announced which was the initial batch of assay results from the
surface drilling at the Big Missouri deposit. Highlights include
98.84 g/t Au over 6.48m from a depth of 51.5m in hole P23-2490,
including 691.50 g/t Au over 0.90m. This is the all-time second
highest-grade drill intercept at Big Missouri and is the Company’s
highest-grade drill intercept property-wide since 2015.
- On July 31, 2023, the Company entered into a master lease
agreement with Caterpillar Financial Services (“CAT Financial”) for
an equipment lease facility up to US$15 million on an uncommitted
basis for surface mining equipment and construction equipment. The
lease terms of the equipment are 4 to 5 years at an interest rate
of the Canadian Dollar Offered Rate plus 4.25%.
- On August 29, 2023, the Company announced positive results from
the 2023 induced polarization (“IP”) geophysics program at PGP.
These results were from 28 IP lines totaling 29 line-kilometers
across three grids. Highlights of the results included a strong IP
anomaly showing potential that the Sebakwe Zone structure extends
approximately 1,000 metres beyond the westernmost extent of surface
drilling from 2022, Day Zone IP signature continuing approximately
800 metres to the north of previous surface drill results and
Dilworth IP showing strong chargeability anomaly to the west and
below where most drilling was previously focused.
- On September 19, 2023, the Company acquired a full-service
laboratory facility (“Assay Lab”) in Stewart, BC from Seacan Labs
Corp. The Assay Lab will be used to perform the testing required by
Ascot for mineral exploration, mining operation, and environmental
monitoring.
- Construction of the new water treatment plant (“WTP”) is
substantially complete. Commissioning process commenced in
October.
- On October 3, 2023, the town council of Stewart, B.C. approved
a Temporary Use Permit (“TUP”) to install a camp facility in the
town to provide additional accommodations for workers at the
Project. The TUP is for a three-year term with potential to renew
for another three years afterwards. The Company quickly started to
mobilize and install living quarters for the camp and expects an
initial capacity of 76 beds to be ready by the end of November. The
addition of bed capacity in the near term is expected to alleviate
some of the pressure caused by the extended earthworks
schedule.
PROJECT CONSTRUCTION
In January 2023, the Company closed a project
financing package consisting of US$110 million as a deposit in
respect of gold and silver streaming agreements (the “Stream”) and
a strategic equity investment (the “Strategic Investment”) of C$45
million, a portion of which is structured as Canadian Development
Expenditures flow through shares, such that the total gross
proceeds to the Company were C$50 million. Upon securing the new
project financing, Ascot re-mobilized various contractors to
progress activities for the remainder of construction scope for the
Project. At the start of Q3 2023, there were approximately 192
employees and contractors working at the project site, and by the
end of the quarter on September 30, 2023, there were over 260
people working at site.
Construction Progress Key Performance
Indicators (“KPI”)At the end of Q3 2023, overall
construction excluding mine development was 66% complete (73% as of
October 31, 2023), compared with 48% complete at the end of Q2
2023. Detailed engineering and procurement are substantially
complete. The Company anticipates the first gold pour by the end of
Q1 2024.
Previously, the Company had anticipated to
complete earthworks by the end of September. The bedrock in the
north dam area was deeper than anticipated and this required the
removal and replacement of ~100,000 bank cubic metres of material
that was not previously planned for. In addition, the drill and
blasting of Cascade Creek Diversion Channel (“CCDC”) for new
construction material was more complicated and took longer than
previously expected. The earthworks contractor is now anticipated
to complete the work by the end of November. The earthworks
contractor’s personnel also increased from the originally planned
70 to 120 people, resulting in an increase in accommodation costs
and delays in ramp up of other construction activities.
Capital costs, including mining costs, incurred
as of September 30, 2023 were $245 million. As of September 30,
2023, the remaining project construction capital required to
complete construction and achieve the first gold pour is
approximately $89 million including mine development costs but
excluding certain pre-operating costs and working capital. This
implies a total project capital cost of $334 million, which is
higher than the most recent total project budget of $310 million as
reported last quarter. The increase is mainly due to the increase
in scope and duration of the earthworks and project indirect
costs.
The company is assessing its working capital
requirements to progress the project from construction to
commissioning, initial production, and ramp-up phases, and is
evaluating various potential financing options.
SafetyThe Project continues to
have an excellent safety record with 865,016 hours of work to the
end of Q3 2023 and zero lost time incidents. The total recordable
incident frequency has been reduced yet again from 0.95 at the end
of Q2 2023 to 0.69 by the end of Q3 2023. In addition, despite the
expanding construction activity on site resulting in a 30% increase
in exposure hours compared to last quarter, the absolute number of
incidents including property damage, first aid injuries, and near
misses, decreased by 12% in Q3 2023. Reporting activity has been
improved, and the Company will continue to work on proactive safety
training and measures to reduce overall incidents at the Project
site.
Processing PlantIn Q3 2023,
mechanical and electrical work in the mill has been substantially
completed. The work in the mill is currently focused on piping and
systems and controls.
The tailings thickener and cyanide destruction
tank outside the mill are mechanically complete. The freshwater
collection point has been constructed and all lines have been
completed to the pumphouse. Piping installation at the mill is over
70% complete. Instrumentation and controls installations are
advancing well. All concrete works have been completed.
Commissioning of some selected subsystems has commenced focusing on
electrical rooms within the mill.
Tailings Storage Facility (“TSF”) and
Cascade Creek Diversion Channel (“CCDC”) EarthworksThe
earthworks contract for the TSF and CCDC was signed in March 2023
and the contractor was mobilized to the site in April 2023. In
order to dewater the tailings facility for the required earthworks,
an additional temporary WTP was mobilized to site and commissioned
in May 2023.
During Q3 2023, the earthworks contractor
focused the reconstruction of the North Dam area where historical
old tailings needed to be removed and underlying bedrock needed to
be exposed and new dam material placed. The bedrock was deeper in
certain areas and this required the removal and replacement of
~100,000 bank cubic metres that was not previously planned for. In
addition, the drilling and blasting of CCDC for new construction
material was more complicated and took longer than previously
expected.
Despite these challenges, the earthworks
contractor completed the North Dam and has completed the liner
install in the North Dam and spillway. Fortunately, the weather
cooperated and now the main focus is on completing the South Dam,
which is expected by the end of November 2023. The earthworks
contractor occupies a significant portion of the site camp
accommodation and this has resulted in delay in bringing other
construction workers to site to focus on other aspects of the
project. To mitigate the impact of this delay, Ascot was successful
in obtaining a temporary use permit to construct a temporary camp
in Stewart, which is expected to be completed in late November
2023.
Water Treatment Plant
(“WTP”)Crews have also made progress on the new WTP and
associated infrastructure, including the clarifier, lime silos,
moving bed bio-reactor (“MBBR”) tanks and other reagent tanks.
Construction of all major pieces of equipment is now complete with
major milestones of mechanical completion tests for the clarifier
and MBBR tanks successful. Most components are being commissioned
in isolation, and upon the delivery and installation of two
additional transformers, full commissioning of the WTP is
anticipated before year-end.
Site InfrastructureDuring Q3
2023, most of the new electrical substation was mechanically
completed. The only remaining component is a protection and control
panel, scheduled to be installed by the end of November. Crews have
completed the 138kV power line to connect to the power grid less
than 500 metres away. All 138kV lines have been pulled and the
physical link up with the BC Hydro grid is currently taking place.
Site electrification is planned for mid-December. Overland piping
is over 70% complete and will be completed once the TSF work area
has been opened. Medium voltage overhead lines are 80% complete and
are expected to be completed in early December 2023.
Mine DevelopmentAs reported
last quarter and after an extensive and competitive process
involving six contracting companies, in August 2023 Ascot selected
Procon Mining & Tunnelling (“Procon”) for a 3-year contract to
advance the underground portion of the project. Procon has
extensive underground mining experience in the province, including
its current mining and development contract at the nearby Brucejack
underground gold mine. In early Q3 2023, Procon began their initial
mobilization to site, which has been planned in cost-effective
stages, and deployed senior project management personnel to
coordinate storage and laydown areas ahead of operating crew
mobilization.
In 2022, work commenced on the Big Missouri
portal and approximately 907 metres of underground development was
completed before being paused for the winter. In August 2023,
Procon brought in mining personnel and equipment to do the initial
work on dewatering of this existing Big Missouri development and
re-establishing mine infrastructure. Currently, Procon is advancing
underground waste and ore development including the decline, which
will eventually connect to the Silver Coin deposit. In advance of
mill start-up in Q1 2024, Ascot will stockpile mineralized material
from Big Missouri in the Dago pit, ready for processing.
In August 2023, surface work commenced on the
new Premier portal close to the mill, including establishing the
start of an access road for waste disposal in the historic Premier
pit. In September 2023, Procon started the portal face preparations
including holes for cable bolts and other ground support and began
clearing a pad area for service infrastructure including gensets
and compressors. Initial underground decline development will start
in November with initial rounds and placement of shotcrete arches
similar to what was done at Big Missouri last year, and will be
advanced down into the Premier deposit for initial mining in the
Prew Zone. The ramp has been strategically laid out to allow for
underground drilling on the Sebakwe Zone next spring and will
eventually connect a footwall ramp over to the 602 area at the
southern end of the Premier deposit. It is anticipated that the
Prew Zone will be accessed in early 2024. This is an integral part
of Ascot’s de-risking strategy to have multiple mining production
sources from two portals when milling operations are started.
Ascot also received various pieces of mine
operating equipment during Q3 2023. For the underground mine,
Procon initially mobilized two jumbos, three 30-tonne haul trucks,
two scoops, and an emulsion loader, in addition to support
equipment such as scissor-decks, flat-decks and telehandlers, with
further equipment to follow in Q4 2023 as the mining area expands.
Ascot itself has purchased the initial two CAT 45-tonne rock trucks
for the surface ore and waste haulage fleet, as well as support
equipment including two front end loaders and a grader, which will
also be used for snow clearing.
RecruitmentAs recruitment
efforts continue to ramp up in the coming months, Ascot continues
to have many qualified candidates applying for open positions.
Encouragingly, local interest is high, as many applications are
coming from candidates in the area of Stewart and northwestern
British Columbia.
During Q3 2023, Ascot made significant
recruitment efforts focusing on mill and maintenance operations.
Recently recruited positions include a Supply Chain and Logistics
Manager, Operations Superintendent and two Site Services
Supervisors. Approximately one third of Ascot’s site-based
employees are Nisga’a citizens.
Permitting and Environmental
ComplianceAs a result of the refinancing and project
slowdown in 2022, a Joint Permit Amendment Application (“JPAA”) was
required to be re-aligned with the project completion dates and was
submitted in October 2023. The JPAA is currently in the government
screening process. In addition, a Mines Act Permit Amendment
(“MAPA”) was submitted in June 2023 with respect to changing the
location of the Premier portal from the southern location to an
area closer to the mill facility, for which the Company received
approval in September 2023.
2023 EXPLORATION PROGRAM
The exploration program commenced on June 21,
2023 when a drill rig was mobilized to the Prew Zone of the Premier
deposit. After 16 holes were drilled totaling 5,347 metres at the
Prew Zone, drilling was moved north to the Big Missouri deposit and
the Day Zone, where a further 72 holes were drilled totaling 6,539
metres. Drilling was completed in late October, and the total 2023
drilling program was comprised of 88 holes totaling approximately
11,886 metres. Assay results from the 2023 drilling season continue
to be received and the Company anticipates releasing results over
the coming months.
The 2023 ground geophysical induced polarization
(“IP”) survey was completed in the summer. The program comprised of
28 IP lines totaling 29 line-kilometers across three grids – one
grid near the Premier mill targeting the western extension of the
Sebakwe Zone, one grid targeting the northern extension of the Day
Zone at the Big Missouri deposit, and one grid testing the strike
and depth extent of the Dilworth deposit. The results were highly
encouraging, and are summarized as follows:
- Strong IP anomaly shows potential that the Sebakwe Zone
structure extends approximately 1,000 metres beyond the westernmost
extent of surface drilling from 2022;
- Day Zone IP signature continues approximately 800 metres to the
north of previous surface drill results, and
- Dilworth IP shows strong chargeability anomaly to the west and
below where most drilling was previously focused.
FINANCIAL RESULTS FOR THE THREE MONTHS
ENDED SEPTEMBER 30, 2023
The Company reported a net loss of $1,473 for Q3
2023 compared to $2,396 for Q3 2022. The lower net loss in current
quarter was mainly driven by lower foreign exchange loss.
LIQUIDITY AND CAPITAL
RESOURCES
As at September 30, 2023, the Company had cash
& cash equivalents of $80,814 and working capital of $42,026
(including current portion of deferred revenue of $8,118 and flow
through premium liability of $4,125). During the nine months ended
September 30, 2023, the Company issued 120,086,206 common shares,
745,000 stock options, and 51,496 deferred share units. Also,
620,250 stock options expired or were terminated, and 55,530 stock
options, 352,006 deferred share units and 721,597 restricted share
units were exercised in the first nine months of 2023.
As at November 9, 2023, the Company had
555,947,352 common shares outstanding, 23,854,048 stock options,
13,710,500 vested share purchase warrants, 1,575,902 deferred share
units, 3,758,731 restricted share units and 108,108 performance
share units outstanding. Also, 25,767,777 unvested Prepayment
Warrants issued to Nebari are outstanding.
MANAGEMENT’S OUTLOOK FOR
2023
Looking forward, the key items for the Company
for the remainder of the year include:
- Completing the earthworks on the TSF and CCDC by the end of
November
- Increasing the number of piping contractors at the mill to
finish the piping and systems and controls at the process plant to
mitigate the impact from the delay in earthworks at the TSF
- Completing the new temporary camp in Stewart
- Fully commissioning the WTP
- Energising the new substation with full connection to the Long
Lake power plant in mid-December
- Advancing the mining development at Big Missouri and at
Premier
- Continuing to ramp up the operating team personnel
- Ensuring there is sufficient capital to complete the project
and provide the working capital for start up at the end of Q1
2024
UPCOMING CONFERENCE
PARTICIPATION
Ascot management will be participating in two
upcoming conferences in Europe and will be conducting presentations
and one-on-one meetings with investors:
- November 13-15 – Precious Metals Summit Zurich,
Switzerland
- November 20-21 – 121 Mining Investment London, UK
CONSTRUCTION PROGRESS
PHOTOS
Figure 1 – Premier Portal
construction
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/21ebe11d-6b80-41d2-9ee9-8f84bfc80deb
Figure 2 – New electrical substation
construction
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/fa614f3e-4f23-4462-afe9-4c6e45bf4bef
Figure 3 – New WTP overview
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/94146c94-390e-4b10-a624-566584d6a529
Figure 4 – New WTP MBBR tanks and
electrical building
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/00dbc413-7f8e-4363-b390-b54171f73da5
Figure 5 – Process plant
interior
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/e7df5666-3470-4e3d-bbeb-b2ebab15ea30
Figure 6 – TSF construction looking
north
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/e0580995-3540-4d7d-b03f-1e46f238d0fa
Figure 7 – TSF spillway liner
installation
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/67761d26-f7b1-4c6c-b5c4-d789092e4492
Figure 8 – TSF north dam liner
installation
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/68437f6a-a0fd-40a6-82af-79ce0491bc43
Qualified Person
John Kiernan, P.Eng., Chief Operating Officer of
the Company is the Company’s Qualified Person (QP) as defined by
National Instrument 43-101 and has reviewed and approved the
technical contents of this news release.
On behalf of the Board of Directors of
Ascot Resources Ltd.“Derek C. White”President &
CEO
For further information
contact:
David Stewart, P.Eng.
VP, Corporate Development & Shareholder
Communications dstewart@ascotgold.com 778-725-1060 ext. 1024
About Ascot Resources Ltd.
Ascot is a Canadian junior exploration and
development company focused on re-starting the past producing
Premier gold mine, located on Nisga’a Nation Treaty Lands, in
British Columbia’s prolific Golden Triangle. Ascot shares trade on
the TSX under the ticker AOT. Concurrent with progressing the
development of Premier, the Company continues to successfully
explore its properties for additional high-grade underground
resources. Ascot is committed to the safe and responsible
development of Premier in collaboration with Nisga’a Nation as
outlined in the Benefits Agreement.
For more information about the Company, please
refer to the Company’s profile on SEDAR+ at www.sedar.ca or visit
the Company’s web site at www.ascotgold.com, or for a virtual tour
visit www.vrify.com under Ascot Resources.
The TSX has not reviewed and does not accept
responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding
Forward-Looking Information
All statements and other information contained
in this press release about anticipated future events may
constitute forward-looking information under Canadian securities
laws ("forward-looking statements"). Forward-looking statements are
often, but not always, identified by the use of words such as
"seek", "anticipate", "believe", "plan", "estimate", "expect",
"targeted", "outlook", "on track" and "intend" and statements that
an event or result "may", "will", "should", "could" or "might"
occur or be achieved and other similar expressions. All statements,
other than statements of historical fact, included herein are
forward-looking statements, including statements in respect of the
advancement and development of the PGP and the timing related
thereto, the exploration of the Company’s properties and
management’s outlook for the remainder of 2023 and beyond. These
statements involve known and unknown risks, uncertainties and other
factors that may cause actual results or events to differ
materially from those anticipated in such forward-looking
statements, including risks associated with the business of Ascot;
risks related to exploration and potential development of Ascot's
projects; business and economic conditions in the mining industry
generally; fluctuations in commodity prices and currency exchange
rates; uncertainties relating to interpretation of drill results
and the geology, continuity and grade of mineral deposits; the need
for cooperation of government agencies and indigenous groups in the
exploration and development of properties and the issuance of
required permits; the need to obtain additional financing to
develop properties and uncertainty as to the availability and terms
of future financing; the possibility of delay in exploration or
development programs and uncertainty of meeting anticipated program
milestones; uncertainty as to timely availability of permits and
other governmental approvals; risks associated with COVID-19
including adverse impacts on the world economy, construction timing
and the availability of personnel; and other risk factors as
detailed from time to time in Ascot's filings with Canadian
securities regulators, available on Ascot's profile on SEDAR+ at
www.sedar.ca including the Annual Information Form of the Company
dated March 23, 2023 in the section entitled "Risk Factors".
Forward-looking statements are based on assumptions made with
regard to: the estimated costs associated with construction of the
Project; the timing of the anticipated start of production at the
Project; the ability to maintain throughput and production levels
at the Premier Mill; the tax rate applicable to the Company; future
commodity prices; the grade of Resources and Reserves; the ability
of the Company to convert inferred resources to other categories;
the ability of the Company to reduce mining dilution; the ability
to reduce capital costs; and exploration plans. Forward-looking
statements are based on estimates and opinions of management at the
date the statements are made. Although Ascot believes that the
expectations reflected in such forward-looking statements and/or
information are reasonable, undue reliance should not be placed on
forward-looking statements since Ascot can give no assurance that
such expectations will prove to be correct. Ascot does not
undertake any obligation to update forward-looking statements. The
forward-looking information contained in this news release is
expressly qualified by this cautionary statement.
Ascot Resources (TSX:AOT)
과거 데이터 주식 차트
부터 1월(1) 2025 으로 2월(2) 2025
Ascot Resources (TSX:AOT)
과거 데이터 주식 차트
부터 2월(2) 2024 으로 2월(2) 2025