Firering Strategic
Minerals plc / EPIC: FRG / Market: AIM / Sector: Mining
5 November 2024
Firering Strategic Minerals
plc
("Firering" or "the
Company")
Quicklime Operational
Update
The first gasifier's arrival marks a
major milestone in Limeco's plant renovation
Firering Strategic Minerals plc, an emerging
quicklime production and critical mineral exploration company, is
pleased to announce an operational update with regards to its
quicklime project in Zambia ("Limeco"), which is being fast-tracked
towards the start of phased commissioning in Q4 2024.
HIGHLIGHTS
· Key modifications to the
first of eight kilns are nearly complete, which will significantly
improve operational efficiency and lower the plant's operating
costs.
· Aggregate crushing operation
continues to perform well, supporting positive cash
flow.
· Positioned to commence
production immediately on commissioning of Kiln 1 in Q4 2024 with
kiln stockpile now standing at +15,000 tonnes.
· Newly built pilot kiln
performing effectively, with promising burn test
results.
· Positive off-take discussions
progressing well, driven by Limeco's strong production capacity and
commitment to quality control, attracting notable market
interest.
· Updated JORC-compliant
Mineral Resource Estimate anticipated in November 2024.
Yuval Cohen,
Chief Executive of Firering, said:
"We are delighted by the
rapid progress at Limeco, including the installation works for the
first gasifier, which marks a key milestone in the plant renovation
strategy. Modifications to the first kiln are nearly complete, with
commissioning of both the kiln and gasifier targeted for Q4 2024.
Laboratory test work has also accelerated, supported by the
completion of a pilot kiln, which has yielded initial quicklime
(CaO) results between 92% and 94%. This progress is driving
productive discussions with prospective clients, and accordingly we
are optimistic about securing long-term offtake
agreements.
"The upcoming
two months promise to be extremely busy as we work toward the
production start target, with a steady stream of news expected.
This includes the release of an updated Mineral Resource Estimate
as Limeco positions itself to meet the rising demand from Zambia's
growing copper production market."
DETAILS
Limeco's quicklime project remains on track for
phased commissioning to start in Q4 2024 with critical
modifications to the first of eight kilns largely complete. Key to
this is the conversion of the fuel source for these kilns from
Heavy Fuel Oil ("HFO") to coal gasification, which will
significantly enhance the operational efficiency and reduce
operating costs of the plant.
Additionally, the aggregate crushing operation
is continuing to perform very well, underpinning positive
operational cashflow as well as providing an increasing stockpile
for the kilns, which is now in excess of 15,000 tonnes.
Coal
gasifier
The first gasifier arrived on site and is now
being erected.
Figure 1: Parts of gasifier arriving at Limeco,
29 October 2024.
Figure 2: Parts of gasifier being off loaded at
lime plant, 29 October 2024.
Figure 3: Erection of gasifier
Modifications
to Kiln 1
Work is progressing well for the commissioning
of Kiln 1 by the end of Q4 2024 with the following activities
concluded or in progress:
Item
|
Status
|
Comment
|
Discharge cone
|
Completed & operational
|
Increased discharge opening
|
Rotary table
|
Completed & operational
|
Modified opening
|
New skip hoist brakes
|
Completed & operational
|
Single drum changed to double
|
New discharge gates
|
Not completed
|
Awaiting arrival on site
|
New burner ports
|
Not completed
|
Arrived & being installed
|
Feed conveyor to skip hoist
|
Completed & operational
|
-
|
Skip hoist
|
Completed & operational
|
-
|
Pan conveyor
|
Completed & operational
|
-
|
Roller crusher
|
Completed & operational
|
-
|
Bucket elevator
|
Completed & operational
|
-
|
Silo discharge end
|
Not completed
|
Work in progress
|
Modified exhaust stack
|
Completed
|
Installed on 30 October 2024
|
Figure 4: View of refurbished hoist structure
(blue) and refurbished skip (orange).
Coal storage
facility
Work on the coal storage facility, from where
the coal will be conveyed to the coal gasifier, is 40%
completed.
Figure 5: View of incline ramp from coal
storage facility to coal gasifier.
Crushing
plant
The newly installed impact crusher is
performing well with over 60,000 tonnes of limestone crushed.
The kiln feed, sized -90mm to +60mm, is stockpiled near the lime
plant and now totals 15,000 tonnes. Furthermore, aggregate
production from the minus 60mm stream is also going well and
contributing 50% to Limeco's positive operational
cashflow.
Figure 6: View of part of the kiln feed with
lime plant in the background.
Laboratory
The recently constructed pilot kiln is
performing well with burn tests giving good results; initial test
results showed available quicklime ranging between 92% and
94%.
Figure 7: Burnt limestone from the pilot kiln
awaiting further testwork to determine available quicklime
(CaO).
Mineral
Resource Estimate
Earthlab Exploration and Mining Consulting
("Earthlab") has been engaged by Firering to update the
current Mineral Resource Estimate ("MRE")
of 73.7Mt @ 95.3% CaCO3
produced by Golder Associates in October 2017.
This update, incorporating data from the recently awarded
392.51 hectare exploration licence adjacent to Limeco's current
licence (see RNS dated 3 September 2024), has the potential
to increase the MRE by between 60Mt to 70Mt at similar
grades. Earthlab's updated JORC compliant report is
expected in November 2024.
Long-term
offtake agreements
Discussions are advancing with clients across
various sectors for long-term offtake agreements. This
includes negotiations with local and regional industries currently
reliant on imported quicklime, principally from South Africa.
Limeco's robust production capacity, combined with its
commitment to quality control, is generating considerable market
interest.
*** ENDS ***
For further information visit
www.fireringplc.com or contact:
Firering
Strategic Minerals
Yuval
Cohen
E:
info@firering-holdings.com
SPARK Advisory
Partners Limited (Nominated Adviser)
Neil Baldwin / James Keeshan / Adam Dawes
T: +44 20 3368 3550
Optiva
Securities Limited (Joint Broker)
Christian Dennis / Daniel
Ingram
T: +44 20 3137 1903
Shard Capital
Partners LLP (Joint Broker)
Damon Heath / Erik
Woolgar
T: +44 20 7186 9950
St Brides
Partners Limited (Financial PR)
Isabel de Salis / Susie Geliher / Seb
Weller
E:
firering@stbridespartners.co.uk
Notes
Firering Strategic Minerals plc is an AIM
listed resource company set to commence commissioning a significant
quicklime project in Zambia in Q4 2024 to produce 600-800 tonnes of
quicklime per day along with ancillary products. With over US$100
million in historical investment, the project is strategically
positioned to support the expanding copper producers in the Zambian
Copper Belt, which are currently reliant on imported quicklime from
South Africa. Firering currently holds an SPA over a 20.5%
stake in Limeco Resources Limited ("Limeco") with 10% already paid
and an option to increase this to 45%. Additionally, the Company is
advancing the Atex Lithium-Tantalum Project in northern Côte
d'Ivoire, an exploration project rich in lithium and
tantalum-niobium, with drilling results indicating significant
resource potential in this established mining
jurisdiction.