7 March 2014 ASX Code: BAB, AIM Code: BGL

CLARIFICATION OF PRODUCTION FORECAST ASSUMPTIONS

In an announcement released this morning regarding a preliminary mining study for the Company's Gibraltar Project, reference was made to forecast gold production for the Bullabulling Gold Project. This production forecast was first released on 15 October 2013. The Gibraltar Project is not included in the Company's production forecast.

Bullabulling Gold Limited wishes to clarify that the production forecast was based on the following material assumptions.

Mineral Resource

The Mineral Resource estimate, presented in Table 1 below, was prepared and first disclosed under the JORC Code 2004 on 19 October 2013.

 
        Table1: Bullabulling Gold Project Mineral Resource Estimate 
                              (0.5g/t cut-off) 
--------------------------------------------------------------------------- 
 Deposit                 Classification   Tonnage     Grade      Cont. Gold 
----------------------  ---------------  ---------  ---------  ------------ 
 Bullabulling Laterite      Inferred       1.7 Mt    0.89 g/t    48,000 oz 
----------------------  ---------------  ---------  ---------  ------------ 
 Bullabulling Primary      Indicated      72.4 Mt    0.98 g/t    2,279,000 
                                                                     oz 
----------------------  ---------------  ---------  ---------  ------------ 
                            Inferred      35.0 Mt    1.12 g/t    1,257,000 
                                                                     oz 
----------------------  ---------------  ---------  ---------  ------------ 
 Bullabulling Total       Ind. & Inf.     109.1 Mt   1.02 g/t    3,584,000 
                                                                     oz 
----------------------  ---------------  ---------  ---------  ------------ 
 

Mining

It was assumed all mining would be carried out by open pit methods using conventional drill and blast techniques with a 400t and a 600t hydraulic excavator loading diesel powered 230t capacity haul trucks. All mining equipment was assumed to be owned and operated by the Company.

 
        Table 2: Bullabulling Preliminary Mine Production Estimate 
               (Diluted Mineral Resource Within Pit Designs) 
-------------------------------------------------------------------------- 
   Indicated Resource       Inferred Resource              Total 
------------------------  ----------------------  ------------------------ 
Tonnes  Grade   Ounces    Tonnes  Grade  Ounces   Tonnes  Grade   Ounces 
------  -----  ---------  ------  -----  -------  ------  -----  --------- 
 79.8   0.82   2,096,000   14.8   0.97   466,000   94.7   0.84   2,562,000 
  Mt     g/t       oz       Mt     g/t      oz      Mt     g/t       oz 
 84%              82%      16%             18%     100%            100% 
------  -----  ---------  ------  -----  -------  ------  -----  --------- 
 

Note that there is a low level of geological confidence associated with inferred mineral resources and there is no certainty that further exploration work will result in the determination of indicated mineral resources or that the production target itself will be realized.

Mining blocks within the production estimate have been diluted by the inclusion of mineralisation below the resource cut-off grade. 345 million tonnes of waste rock is mined over an estimated life of mine of approximately 13 years at an average strip ratio of 3.6:1.

Processing

Processing was assumed to take place via an on-site purpose built carbon in leach plant at an annual rate of 7.5 million tonnes of ore per annum. Average recovery over the life of mine was 87.3%. Metallurgical recovery was derived from test work and an examination of production performance during previous production at the site using a similar CIL plant.

Over the life of mine 2,237,500ounces of gold were forecast to be recovered at an average rate of 175,000 ounces per annum.

Financial Assumptions

The estimates of capital and operating costs are presented in Tables 3 and 4 below.

 
 Table 3: Bullabulling Preliminary Capital 
  Cost Estimate 
--------------------------------------------- 
 Fixed Plant & Infrastructure         $326.4M 
-----------------------------------  -------- 
 Establishment & Pre-production 
  Mining                               $32.4M 
-----------------------------------  -------- 
 Mobile Equipment - Pre-production     $81.6M 
-----------------------------------  -------- 
 Mobile Equipment - Additions          $10.5M 
-----------------------------------  -------- 
 Sustaining Capital                    $54.4M 
-----------------------------------  -------- 
 
 
 Table 4: Bullabulling Preliminary Operating 
  Cost Estimate 
---------------------------------------------- 
 Mining                                $9.33/t 
----------------------------  ---------------- 
 Processing                           $12.27/t 
----------------------------  ---------------- 
 Administration                        $0.15/t 
----------------------------  ---------------- 
 Refining                              $0.04/t 
----------------------------  ---------------- 
 

A fixed gold price of A$1,500 per ounce was assumed over the life of mine.

For information, contact:

 
 Brett Lambert                    Westhouse Securities Limited 
  Bullabulling Gold Limited        (UK Broker & Nominated Adviser) 
  Level 2, 55 Carrington Street    Martin Davison / Dominic Palmer-Tomkinson 
  Nedlands, WA, 6009, Australia    / Hugo Rubinstein 
  Tel: +61 8 9386 4086             Tel: +44 20 7601 6100 
-------------------------------  ----------------------------------------------- 
 Neil Boom                        John Gardner / Rupert Dearden 
  Gresham PR Ltd (UK media)        MAGNUS Investor Relations. Corporate 
  Tel: +44 7866 805 108            Communication. (Australian Media) 
                                   Tel: +61 8 6160 4900 
                                   jgardner@magnus.net.au rdearden@magnus.net.au 
-------------------------------  ----------------------------------------------- 
 

Competent Person Statement

The information in this report that relates to the Exploration Results, Mineral Resources or Ore Reserves is based upon information compiled by Mr Trevor Pilcher, who is a full time employee of the Company and is a member of The Australasian Institute of Mining and Metallurgy. Mr Pilcher has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and the activity in which he is undertaking to qualify as a Competent Person under 2012 Edition of the Australasian Code for Reporting Exploration Results, Mineral Resources and Ore Reserves (JORC Code). Mr Pilcher consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.

The information in this report that relates to the Exploration Results, Mineral Resources or Ore Reserves was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. All material assumptions and technical parameters underpinning the estimates of mineral resources continue to apply and have not materially changed.

This information is provided by RNS

The company news service from the London Stock Exchange

END

MSCKDLBBZXFBBBQ

Bullabulling (LSE:BGL)
과거 데이터 주식 차트
부터 6월(6) 2024 으로 7월(7) 2024 Bullabulling 차트를 더 보려면 여기를 클릭.
Bullabulling (LSE:BGL)
과거 데이터 주식 차트
부터 7월(7) 2023 으로 7월(7) 2024 Bullabulling 차트를 더 보려면 여기를 클릭.