By Dominic Chopping

 

Vestas Wind Systems said Tuesday it has received a firm order for six wind turbines for the Bjornstrup wind park in Midtjylland, Denmark.

The order from Hofor consists of six V136-4.5 megawatt turbines and includes supply, delivery, and commissioning as well as a long-term service agreement.

Turbine delivery is expected to begin in the fourth quarter of 2024 with commissioning scheduled for completion in the second quarter of 2025.

Financial terms weren't disclosed.

 

Write to Dominic Chopping at dominic.chopping@wsj.com

 

(END) Dow Jones Newswires

September 19, 2023 08:05 ET (12:05 GMT)

Copyright (c) 2023 Dow Jones & Company, Inc.