Aker Solutions, Siemens Energy, Doosan Babcock Consortium Get UK Power Station Contract
16 6월 2022 - 4:33PM
Dow Jones News
By Dominic Chopping
Aker Solutions ASA said Thursday that as part of a consortium
with Siemens Energy AG and Doosan Babcock, it has been awarded the
front-end engineering and design contract for SSE Thermal and
Equinor ASA's proposed Keadby 3 Carbon Capture Power Station in the
U.K.
Over the next 12 months, the consortium will deliver the
engineering design for the proposed natural gas power plant--with a
generating capacity of up to 910 megwatts--that is to be equipped
with a carbon-capture plant to remove CO2 from its emissions.
Aker Carbon Capture ASA will be the consortium's carbon-capture
provider.
Keadby 3, located in North Lincolnshire, will have the ability
to capture up to 1.5 million metric tons of carbon annually once it
is operational, which represents around 5% of the government's 2030
target.
Aker Solutions said it will book the contract as order intake in
the second quarter of 2022.
Financial terms weren't disclosed.
Write to Dominic Chopping at dominic.chopping@wsj.com
(END) Dow Jones Newswires
June 16, 2022 03:18 ET (07:18 GMT)
Copyright (c) 2022 Dow Jones & Company, Inc.
SSE (PK) (USOTC:SSEZY)
과거 데이터 주식 차트
부터 11월(11) 2024 으로 12월(12) 2024
SSE (PK) (USOTC:SSEZY)
과거 데이터 주식 차트
부터 12월(12) 2023 으로 12월(12) 2024
SSE PLC (PK) (OTC 시장)의 실시간 뉴스: 최근 기사 0
More SSE PLC (PK) News Articles