Aurcana Provides Construction Update and Production Outlook for Its Revenue Virginius Mine for the Remainder of 2021
04 5월 2021 - 10:00PM
AURCANA SILVER CORPORATION ("
Aurcana" or the
"
Company") (TSXV: AUN, OTCQX: AUNFF) is
pleased to provide a construction update and a production outlook
for the remainder of 2021 for its Revenue Virginius Mine, (RV)
located near Ouray, Colorado.
Mine Development
- Underground mine
development is proceeding on schedule with three raises being
driven vertically from the 2000 main haulage level 800 feet to the
1200 level (See Figure 1 below).
-
The #1 Alimak raise is advancing vertically at an average rate
exceeding 16 feet per day and is scheduled to be complete by late
May, after which the hoist and shaft timber will be installed for
permanent men and material access.
-
The #2 Alimak raise has progressed up to the 1500 level and is
temporarily being used for men and materials transport from the
2000 level to the 1800 and 1500 level pending completion of #1
Alimak raise.
-
The #3 Alimak raise vertical development began in May and is
scheduled to reach the 1800 level by the third week of May.
-
On completion of #1 Alimak raise, the #2 and #3 Alimak raises will
be dedicated ore and waste raises.
-
Level (horizontal) development has commenced on the 1800 level to
intersect the Virginius vein, which is scheduled to occur during
the third week of May. Following this, development will continue by
driving drifts both north and south on vein for over 1000 feet to
prepare for stope development.
-
Stope development on the 1800 level is estimated to begin in late
June with first ore to the mill in early July.
-
Ore development on 1800 level is on schedule to deliver initial ore
to the processing plant in July. Two stopes (mining blocks) on the
1800 level will provide the initial ore supply while stopes on the
1500 level are developed.
-
It is anticipated that four stopes will be available by year end
2021 (two stopes per level) to supply the processing plant. However
only two stopes are required to provide the 270 tons per day as
specified in the 2018 feasibility study (the “2018 FS”) prepared in
accordance with National Instrument NI 43-101 – Standards of
Disclosure for Mineral Projects (“NI 43-101”). A copy of the 2018
FS is posted on the Company’s website www.aurcana.com and is also
available on the Company’s profile on SEDAR at www.sedar.com.
Processing Plant
Preparation
- All processing
plant upgrades including installing additional flotation capacity,
replacing cyclones with sizing screens, installing a rod mill,
installing crushers and conveyors along with a new instrument
control system will be completed by mid-June. Processing plant
commissioning with water is scheduled for the last week of June
with first ore through the processing plant in the second week of
July.
- Final work on the
transition chute from the coarse ore bin to the new primary pan
feeder is scheduled to be completed by July 10th, 2021 and will
enable full processing plant operation.
- Throughput will be
ramped up over the course of July to reach 111 tons per day (tpd)
during August, and then to the full production level of 270 tpd
during September.
- Concentrate
shipments will be in 100 ton lots and are anticipated to begin in
early August. Trafigura Trading LLC is the off-taker for 100% of
the concentrates and will pay the value of 95% of the contained
metals based on the mine site concentrate assays at the time of
shipment, with final settlement based on smelter returns.
- Payable silver
equivalent1 production for the period between August to December
2021 is anticipated to be 1,300,000-1,600,000 ounces at an
estimated cash operating costs of between USD10.00 to USD12.00/oz
silver after by-product credits2.
Qualified Person Statement
The scientific and technical content of this
news release was reviewed and approved by Michael Gross, P. Geo, a
“qualified person” within the meaning of NI 43-101
ABOUT AURCANA CORPORATION
Aurcana Corporation owns the Revenue-Virginius
Mine, in Colorado, and the Shafter-Presidio Silver Project in
Texas, US. The primary resource at Shafter and Revenue-Virginius is
silver. Both are fully permitted for production.
ON BEHALF OF THE BOARD OF DIRECTORS OF AURCANA CORPORATION
“Kevin Drover”President & CEO
For further information, visit the website at www.aurcana.com or
contact:
Aurcana Corporation850 – 789 West Pender StreetVancouver, BC V6C
1H2Phone: (604) 331-9333
Gary Lindsey, Corporate CommunicationsPhone:
(720)-273-6224Email: gary@strata-star.com
CAUTIONARY NOTES
This press release contains forward looking
statements within the meaning of applicable securities laws. The
use of any of the words “anticipate”, “plan”, “continue”, “expect”,
“estimate”, “objective”, “may”, “will”, “project”, “should”,
“predict”, “potential” and similar expressions are intended to
identify forward looking statements. In particular, this press
release contains forward looking statements concerning, without
limitation, statements relating to the Private Placement (including
with respect to the timing of closing of the Private Placement).
Although the Company believes that the expectations and assumptions
on which the forward looking statements are based are reasonable,
undue reliance should not be placed on the forward looking
statements because the Company cannot give any assurance that they
will prove correct. Since forward looking statements address future
events and conditions, they involve inherent assumptions, risks and
uncertainties. Actual results could differ materially from those
currently anticipated due to a number of assumptions, factors and
risks. These assumptions and risks include, but are not limited to,
assumptions and risks associated with the receipt of regulatory or
shareholder approvals, and risks related to the state of financial
markets or future metals prices.
Management has provided the above summary of
risks and assumptions related to forward looking statements in this
press release in order to provide readers with a more comprehensive
perspective on the Company’s future operations. The Company’s
actual results, performance or achievement could differ materially
from those expressed in, or implied by, these forward looking
statements and, accordingly, no assurance can be given that any of
the events anticipated by the forward looking statements will
transpire or occur, or if any of them do so, what benefits the
Company will derive from them. These forward looking statements are
made as of the date of this press release, and, other than as
required by applicable securities laws, the Company disclaims any
intent or obligation to update publicly any forward looking
statements, whether as a result of new information, future events
or results or otherwise.
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
1 Silver equivalent is based on the April 2021 average COMEX
prices of Ag USD25.6534/oz, Au USD1,759.47/oz, Cu USD4.2281/lb, Pb
USD0.9152/lb and Zn SDU1.2849/lb; includes payability and payment
timing of the Trafigura offtake contract.
2 By-product credit metal pricing is the same as Silver
equivalent pricing
A graphic accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/9df5d571-1159-4008-99e5-a7a9eebf5b41
Aurcana Silver (TSXV:AUN)
과거 데이터 주식 차트
부터 12월(12) 2024 으로 1월(1) 2025
Aurcana Silver (TSXV:AUN)
과거 데이터 주식 차트
부터 1월(1) 2024 으로 1월(1) 2025